Exam Code: 800-150

Exam Name: Supporting Cisco Devices for Field Technicians

Certification Provider: Cisco

Cisco 800-150 Questions & Answers

Reliable & Actual Study Materials for 800-150 Exam Success

100 Questions & Answers with Testing Engine

"800-150: Supporting Cisco Devices for Field Technicians" Testing Engine covers all the knowledge points of the real Cisco 800-150 exam.

The latest actual 800-150 Questions & Answers from Pass4sure. Everything you need to prepare and get best score at 800-150 exam easily and quickly.

exam =7
Guarantee

Satisfaction Guaranteed

Pass4sure has a remarkable Cisco Candidate Success record. We're confident of our products and provide no hassle product exchange. That's how confident we are!

99.3% Pass Rate
Was: $137.49
Now: $124.99

Cisco 800-150 Practice Test 53

Question 520

Regional north-campus service window. Field report: An installed optic is recognized but an uplink cannot negotiate the planned speed. Which action is the most defensible first step?

  1. Force an arbitrary faster speed unsupported by the optic.
  2. Verify transceiver and interface speed compatibility with the hardware matrix.
  3. Modify endpoint VLAN names to improve optical negotiation.
  4. Change the device login banner as an interface compatibility fix.

Explanation

Correct Answer

B:

Ports and transceivers have supported speeds and media requirements. The action should lead to evidence that the two ends use supported modes and the expected link rate.

Incorrect Answers

A:

This alternative would not solve the reported problem. Ports and transceivers have supported speeds and media requirements. The field team must instead establish whether the two ends use supported modes and the expected link rate.

C:

That change addresses a different aspect of the environment and leaves this requirement unresolved: an installed optic is recognized but an uplink cannot negotiate the planned speed. The relevant control is verify transceiver and interface speed compatibility with the hardware matrix.

D:

Attempting this shortcut is not an adequate substitute for the required action. Ports and transceivers have supported speeds and media requirements. Post-change evidence is still needed.

Question 521

Customer branch-site maintenance. Field report: A server uses a converged network adapter carrying LAN and storage traffic on supported links. Which action is the most defensible first step?

  1. Assume ordinary Ethernet hubs inherently provide native FC zoning.
  2. Attach a fiber optic cable without checking storage protocol support.
  3. Identify FCoE or other qualified convergence features and fabric boundaries.
  4. Delete storage multipathing because a single wire carries multiple traffic classes.

Explanation

Correct Answer

C:

Converged fabrics still need appropriate protocol support, traffic control and storage policy. The action should lead to evidence that supported LAN/storage connectivity and isolation for each traffic type.

Incorrect Answers

A:

This alternative would not solve the reported problem. Converged fabrics still need appropriate protocol support, traffic control and storage policy. The field team must instead establish whether supported LAN/storage connectivity and isolation for each traffic type.

B:

That change addresses a different aspect of the environment and leaves this requirement unresolved: a server uses a converged network adapter carrying lan and storage traffic on supported links. The relevant control is identify fcoe or other qualified convergence features and fabric boundaries.

D:

Attempting this shortcut is not an adequate substitute for the required action. Converged fabrics still need appropriate protocol support, traffic control and storage policy. Post-change evidence is still needed.

Question 522

Primary data-center night shift. Field report: A meeting requires conferencing resources rather than only point-to-point call registration. Which action is the most defensible first step?

  1. Use the DHCP relay as the conference media bridge.
  2. Treat TFTP as a multiparty conferencing application.
  3. Assume a switch MAC table mixes conference audio.
  4. Identify Cisco Meeting Server conferencing capability in the on-premises architecture.

Explanation

Correct Answer

D:

Conference bridging and multiparty meeting media differ from simple endpoint registration. The action should lead to evidence that the conference accepts the authorized participants and media streams.

Incorrect Answers

A:

That change addresses a different aspect of the environment and leaves this requirement unresolved: a meeting requires conferencing resources rather than only point-to-point call registration. The relevant control is identify cisco meeting server conferencing capability in the on-premises architecture.

B:

Attempting this shortcut is not an adequate substitute for the required action. Conference bridging and multiparty meeting media differ from simple endpoint registration. Post-change evidence is still needed.

C:

This alternative would not solve the reported problem. Conference bridging and multiparty meeting media differ from simple endpoint registration. The field team must instead establish whether the conference accepts the authorized participants and media streams.

Question 523

Headquarters wiring-closet visit. Field report: A field visit includes checking an active long-range fiber transmission link. Which action is the most defensible first step?

  1. Use approved optical instrumentation and never look into a powered fiber connector.
  2. Remove safety labels so the connector is easier to see.
  3. Inspect the optical core directly by eye to estimate laser power.
  4. Use a copper network cable tester as a substitute for laser safety.

Explanation

Correct Answer

A:

Fiber transceivers may emit hazardous light invisible to the eye. The action should lead to evidence that optical testing completed without direct viewing of energized fiber.

Incorrect Answers

B:

That change addresses a different aspect of the environment and leaves this requirement unresolved: a field visit includes checking an active long-range fiber transmission link. The relevant control is use approved optical instrumentation and never look into a powered fiber connector.

C:

This alternative would not solve the reported problem. Fiber transceivers may emit hazardous light invisible to the eye. The field team must instead establish whether optical testing completed without direct viewing of energized fiber.

D:

Attempting this shortcut is not an adequate substitute for the required action. Fiber transceivers may emit hazardous light invisible to the eye. Post-change evidence is still needed.

Question 524

Colocation site RMA handoff. Field report: A storage team needs dedicated Fibre Channel SAN switching. Which action is the most defensible first step?

  1. Use a campus access Catalyst switch as the sole native Fibre Channel fabric.
  2. Choose an appropriate Cisco MDS SAN switch or director.
  3. Use a wireless controller for FC zoning.
  4. Place a Webex calling gateway in the storage path.

Explanation

Correct Answer

B:

Cisco MDS platforms serve SAN Fibre Channel switching and fabric management. The action should lead to evidence that intended FC ports, VSAN membership and storage connectivity.

Incorrect Answers

A:

This alternative would not solve the reported problem. Cisco MDS platforms serve SAN Fibre Channel switching and fabric management. The field team must instead establish whether intended FC ports, VSAN membership and storage connectivity.

C:

Attempting this shortcut is not an adequate substitute for the required action. Cisco MDS platforms serve SAN Fibre Channel switching and fabric management. Post-change evidence is still needed.

D:

That change addresses a different aspect of the environment and leaves this requirement unresolved: a storage team needs dedicated fibre channel san switching. The relevant control is choose an appropriate cisco mds san switch or director.

Question 525

Remote office replacement window. Field report: Two managed room endpoints connect but cannot establish an acceptable media format. Which action is the most defensible first step?

  1. Replace the routed underlay without inspecting media negotiation.
  2. Disable device registration to force a better video codec.
  3. Check supported endpoint/media capabilities and configured call settings.
  4. Assume all call signaling responses guarantee codec compatibility.

Explanation

Correct Answer

C:

Video sessions require mutually supported codecs/media parameters as well as signaling. The action should lead to evidence that a test conference negotiates supported video and audio media.

Incorrect Answers

A:

That change addresses a different aspect of the environment and leaves this requirement unresolved: two managed room endpoints connect but cannot establish an acceptable media format. The relevant control is check supported endpoint/media capabilities and configured call settings.

B:

Attempting this shortcut is not an adequate substitute for the required action. Video sessions require mutually supported codecs/media parameters as well as signaling. Post-change evidence is still needed.

D:

This alternative would not solve the reported problem. Video sessions require mutually supported codecs/media parameters as well as signaling. The field team must instead establish whether a test conference negotiates supported video and audio media.

Question 526

Disaster-recovery facility inspection. Field report: A technician must reach a remote device CLI over an approved secured management path. A colleague proposes: “Use Telnet over public Internet when policy requires encrypted management.” Which technical assessment is best supported?

  1. The proposed shortcut is sufficient because send plaintext passwords in an icmp echo payload.
  2. The original problem can be treated as resolved from inventory labels alone, without checking ssh remote access behavior.
  3. There is no need to validate the reported dependency once rely on a web browsing session to configure an unavailable ssh service.
  4. The proposal overlooks the reported dependency: SSH protects interactive device management with authenticated encrypted transport.

Explanation

Correct Answer

D:

The alternative does not address the actual reported dependency. SSH protects interactive device management with authenticated encrypted transport. The supported intervention is use ssh with authorized credentials on the management network; acceptance should show that a permitted SSH session authenticates to the correct device.

Incorrect Answers

A:

The proposed step “Send plaintext passwords in an ICMP echo payload” is not the required mechanism.

B:

The failure described in the field report requires a functional check that a permitted SSH session authenticates to the correct device.

C:

It assumes an unrelated action establishes service recovery. Nothing about “Rely on a web browsing session to configure an unavailable SSH service” demonstrates whether a permitted SSH session authenticates to the correct device.

Question 527

Main campus hardware-service ticket. Field report: A UCS domain's hardware is healthy after RMA but a server profile association is missing. The approved intervention is complete. What observation provides the strongest technical acceptance evidence?

  1. Demonstrate that the intended profile is associated and operational.
  2. Confirm the site inventory list still contains the hostname, without validating the reported service.
  3. Confirm only that the technician attempted: reconfigure an unrelated meeting tenant to create blade identity.
  4. Confirm only that the work ticket says “completed,” without testing ucs management state.

Explanation

Correct Answer

A:

The intended profile is associated and operational. UCS service profiles and management assignments can be essential to expected server identity.

Incorrect Answers

B:

Confirm that the intended profile is associated and operational. UCS service profiles and management assignments can be essential to expected server identity.

C:

For example, “Reconfigure an unrelated meeting tenant to create blade identity” does not demonstrate the corrected technical state.

D:

Check whether the intended profile is associated and operational. UCS service profiles and management assignments can be essential to expected server identity.

Question 528

Regional north-campus service window. Field report: Several racks share an end-of-row network switch design. The shift lead must choose a return-to-service note for this ticket. Which handoff is technically adequate?

  1. Close after recording “Assume all racks must contain a full distribution switch regardless of design” without checking that rack links terminate at the assigned row aggregation ports.
  2. Perform or retain the approved action: map individual rack links to the intended end-of-row aggregation platform; document evidence that rack links terminate at the assigned row aggregation ports.
  3. Apply “Replace rack fiber bundles with unqualified USB cables” as a substitute and declare success from shipment receipt alone.
  4. Defer service verification after “Connect server storage NICs only through a phone gateway” until the next reported incident.

Explanation

Correct Answer

B:

This handoff preserves the required corrective action and the verifiable service outcome. EoR aggregates multiple racks through a planned switch placement rather than ToR per cabinet. Recording that rack links terminate at the assigned row aggregation ports makes the signoff testable.

Incorrect Answers

A:

This proposes a different action with no acceptance evidence. “Assume all racks must contain a full distribution switch regardless of design” cannot replace the validated measure that rack links terminate at the assigned row aggregation ports.

C:

Delivery paperwork describes logistics, not recovered functionality. “Replace rack fiber bundles with unqualified USB cables” leaves the technical requirement and its validation unresolved.

D:

A future incident is not a reasonable acceptance gate for a known problem. “Connect server storage NICs only through a phone gateway” is not evidence that rack links terminate at the assigned row aggregation ports.

Question 529

Customer branch-site maintenance. Field report: A console session displays garbled characters even though power and cable are correct. The approved intervention is complete. What observation provides the strongest technical acceptance evidence?

  1. Confirm only that the technician attempted: change access vlan membership to correct serial stop bits.
  2. Confirm the site inventory list still contains the hostname, without validating the reported service.
  3. Demonstrate that legible console text with correct baud and terminal parameters.
  4. Confirm only that the work ticket says “completed,” without testing terminal baud settings.

Explanation

Correct Answer

C:

Legible console text with correct baud and terminal parameters. Incorrect serial framing or speed can corrupt terminal output.

Incorrect Answers

A:

For example, “Change access VLAN membership to correct serial stop bits” does not demonstrate the corrected technical state.

B:

Confirm that legible console text with correct baud and terminal parameters.

D:

Check whether legible console text with correct baud and terminal parameters.

Question 530

Primary data-center night shift. Field report: A replacement edge platform comes online but a subscribed WAN feature is inactive. Which action is the most defensible first step?

  1. Change an unrelated DNS TTL to recover subscription state.
  2. Assume copied router configuration also transfers all licensing records automatically.
  3. Swap the UPS battery to authorize the feature.
  4. Review feature entitlement and platform registration after configuration restoration.

Explanation

Correct Answer

D:

Replacement hardware may require separate licensing and identity checks. The action should lead to evidence that the required feature is entitled and works on the replacement.

Incorrect Answers

A:

Attempting this shortcut is not an adequate substitute for the required action. Replacement hardware may require separate licensing and identity checks. Post-change evidence is still needed.

B:

This alternative would not solve the reported problem. Replacement hardware may require separate licensing and identity checks. The field team must instead establish whether the required feature is entitled and works on the replacement.

C:

That change addresses a different aspect of the environment and leaves this requirement unresolved: a replacement edge platform comes online but a subscribed wan feature is inactive. The relevant control is review feature entitlement and platform registration after configuration restoration.