Question 710
During a cross-functional security decision at a regional utilities holding company, audit findings are marked closed when teams promise future patches. A manager proposes this quick fix: “close findings on the strength of planned completion dates.” What is the MOST important reason to reject that as the primary treatment?
Explanation
Correct Answer
Future intention does not establish corrective control operation. Require remediation evidence and retesting before verified closure.
Incorrect Answers
Misclassification distorts deadlines, audit findings, and investment. The shortcut under scrutiny is: Future intention does not establish corrective control operation.
Conflicted reporting can conceal significant exposures. The shortcut under scrutiny is: Future intention does not establish corrective control operation.
Uniform testing can miss highest-exposure processes. The shortcut under scrutiny is: Future intention does not establish corrective control operation.