Question 20
At a scheduled executive risk committee for an international logistics platform, an enterprise security program has ten overlapping initiatives and no accountable sequencing. A manager proposes this quick fix: “fund all initiatives equally without dependency analysis.” What is the MOST important reason to reject that as the primary treatment?
Explanation
Correct Answer
Concurrent uncoordinated work can cause resource and control gaps. Define a prioritized program roadmap with dependencies, owners, and benefits.
Incorrect Answers
Unmanaged changes can invalidate risk and delivery estimates. The shortcut under scrutiny is: Concurrent uncoordinated work can cause resource and control gaps.
Shared responsibility leaves material customer obligations. The shortcut under scrutiny is: Concurrent uncoordinated work can cause resource and control gaps.
Stale scope can generate misleading compliance evidence. The shortcut under scrutiny is: Concurrent uncoordinated work can cause resource and control gaps.