Question 190
At a scheduled executive risk committee for an international logistics platform, a change control board approves major production security changes without operational rollback ownership. A manager proposes this quick fix: “leave rollback planning to whoever is on call at failure time.” What is the MOST important reason to reject that as the primary treatment?
Explanation
Correct Answer
Unassigned recovery action increases outage duration. Require rehearsed rollback roles and acceptance tests before cutover.
Incorrect Answers
Undocumented scope reduction conceals residual risk. The shortcut under scrutiny is: Unassigned recovery action increases outage duration.
Unverified supplier metrics can conceal missed commitments. The shortcut under scrutiny is: Unassigned recovery action increases outage duration.
Unrecorded resolutions impede assurance and lessons learned. The shortcut under scrutiny is: Unassigned recovery action increases outage duration.