Question 390
In a discussion with the delivery team on a predictive initiative, a data-platform team has a justified scope change but plans to use management reserve without sponsor review. Which assignment establishes appropriate accountability for the affected decision?
Explanation
Correct Answer
Have the authorized sponsor approve use of management reserve and baseline changes. The selected owner has authority over the specific business decision instead of transferring responsibility to an unrelated function. In this case, management reserve is subject to defined authority and change control. The stated constraint is: A data-platform team has a justified scope change but plans to use management reserve without sponsor review. The chosen accountability is the most direct response under these conditions.
Incorrect Answers
Have procurement confirm escalation terms and sponsor approve revised financial response. This response addresses another situation in the same task area: A construction cost forecast uses last year's material prices despite newly signed inflation-linked supplier terms. There, defensible forecasts must reflect binding commercial terms rather than obsolete assumptions. For the current situation—A data-platform team has a justified scope change but plans to use management reserve without sponsor review—this option would leave the specific need unresolved: management reserve is subject to defined authority and change control.
Have the project manager and finance partner present corrective options to sponsor. This response addresses another situation in the same task area: A fixed-price project has a schedule slip that increases internal labor even though vendor invoice totals are unchanged. There, total project cost includes internal delivery consequences beyond supplier bills. For the current situation—A data-platform team has a justified scope change but plans to use management reserve without sponsor review—this option would leave the specific need unresolved: management reserve is subject to defined authority and change control.
Have finance controller validate forecast and sponsor decide affordability response. This response addresses another situation in the same task area: A project reports spending below budget because key equipment invoices are late, while commitments already exceed the cap. There, cash timing differences can hide obligations and do not prove financial performance. For the current situation—A data-platform team has a justified scope change but plans to use management reserve without sponsor review—this option would leave the specific need unresolved: management reserve is subject to defined authority and change control.