Question 460
During a regional deployment expansion at a media technology business, engineers report the following issue: A server rack has a separate management port but it is connected to the public service network. The affected work supports language and visual-content AI services; different workloads compete for shared acceleration and storage. Choose TWO: one corrective approach and one result demonstrating it works. (Select TWO.)
Explanation
Correct Answers
Correct corrective action. Separate out-of-band host and switch management from high-volume AI workload traffic and restrict access to authorized operators. This fits the specific reported issue: A server rack has a separate management port but it is connected to the public service network. The corresponding failure being reduced is: Combining privileged management services with general workload networks increases exposure and makes recovery harder during production-fabric failure.
Correct independent evidence. An authorized operator reaches BMC and fabric management over the intended isolated path while workload accounts cannot. This verifies the corrective approach for the affected language and visual-content AI services instead of treating an architecture diagram alone as success.
Incorrect Answers
Not the most direct the action-and-evidence pair for these facts. Estimate model weights, gradients, optimizer state, activations and batch size against usable GPU memory before selecting training hardware. This choice concerns gpu memory capacity for model training and may be valid in another design. But this case reports 'A server rack has a separate management port but it is connected to the public service network', which calls for reasoning about management network isolation and access. The targeted response is: Separate out-of-band host and switch management from high-volume AI workload traffic and restrict access to authorized operators.
Not the most direct the action-and-evidence pair for these facts. Size east-west bandwidth, latency and oversubscription for distributed GPU training based on communication patterns rather than only user-facing north-south traffic. This choice concerns east-west ai data center network requirements and may be valid in another design. But this case reports 'A server rack has a separate management port but it is connected to the public service network', which calls for reasoning about management network isolation and access. The targeted response is: Separate out-of-band host and switch management from high-volume AI workload traffic and restrict access to authorized operators.
Not the most direct the action-and-evidence pair for these facts. A controlled facility-failure review traces each critical path and confirms an acceptable alternate path or documented recovery procedure. This choice concerns redundant facility services for ai availability and may be valid in another design. But this case reports 'A server rack has a separate management port but it is connected to the public service network', which calls for reasoning about management network isolation and access. The targeted response is: Separate out-of-band host and switch management from high-volume AI workload traffic and restrict access to authorized operators.