Question 170
A new tenant floor requests six leaf uplinks but fabric spines are fully committed to existing racks. Which design or operational principle best explains this behavior?
Explanation
Correct Answer
total spine capacity includes available physical ports and supported link-speed and topology constraints. Here, a new tenant floor requests six leaf uplinks but fabric spines are fully committed to existing racks. A useful discriminating check is to review consumed spine port counts, interface maps and oversubscription projections.
Incorrect Answers
That choice—“Rack types are reusable logical patterns for leaf topology and attached systems within a blueprint”—addresses this other problem: An Apstra design must deploy 12 racks with uniform leaf roles and uplink constraints. Here the scenario is: A new tenant floor requests six leaf uplinks but fabric spines are fully committed to existing racks. Total spine capacity includes available physical ports and supported link-speed and topology constraints. The controlling principle is “Total spine capacity includes available physical ports and supported link-speed and topology constraints”.
“Physical topology diversity is necessary to avoid a common point of failure when rack redundancy is required” is associated with a distinct issue: A dual leaf rack is expected to provide application diversity but both uplinks terminate on the same physical spine. By contrast, the actual problem is: A new tenant floor requests six leaf uplinks but fabric spines are fully committed to existing racks. Total spine capacity includes available physical ports and supported link-speed and topology constraints. The controlling principle is “Total spine capacity includes available physical ports and supported link-speed and topology constraints”.
“Rack type and leaf selection must support the intended redundant attachment topology and host interface roles” is relevant to a different condition: A storage workload requires dual-homed servers but a proposed rack type provides only one access leaf. The stated question instead concerns: A new tenant floor requests six leaf uplinks but fabric spines are fully committed to existing racks. Total spine capacity includes available physical ports and supported link-speed and topology constraints. The controlling principle is “Total spine capacity includes available physical ports and supported link-speed and topology constraints”.