Question 280
In the next assurance review, the team has started remediation after finding that a security engineer signs a risk-acceptance form for a loss affecting the sales division. Which measurement would be most relevant for judging whether the exposure is reducing?
Explanation
Correct Answer
Measure risk acceptances signed outside delegated authority. Technical expertise informs decisions but does not confer business risk authority.
Incorrect Answers
Provider responsibilities need an accountable enterprise interface. The deciding difference is “incidents, but no internal function handles business escalation” versus “form for a loss affecting the sales division”.
The control implementer cannot automatically accept the enterprise risk. That is a different operating condition from “form for a loss affecting the sales division”: “records for four departments, with no risk owner”.
Responsibility for control operation differs from ownership of business loss. It serves “ownership from the business processes relying on it”, not “form for a loss affecting the sales division”.