mcAfee Secure Website
23

Isaca CISM Bundle

Exam Code: CISM

Exam Name Certified Information Security Manager

Certification Provider: Isaca

Corresponding Certification: CISM

CISM Training Materials $44.99

Reliable & Actual Study Materials for CISM Exam Success

The Latest CISM Exam Questions as Experienced in the Actual Test!

  • 24
    Questions & Answers

    CISM Questions & Answers

    1228 Questions & Answers

    Includes questions types found on actual exam such as drag and drop, simulation, type in, and fill in the blank.

  • 25
    CISM Video Course

    CISM Training Course

    388 Video Lectures

    Based on Real Life Scenarios which you will encounter in exam and learn by working with real equipment.

  • exam =30
    Study Guide

    CISM Study Guide

    817 PDF Pages

    Study Guide developed by industry experts who have written exams in the past. They are technology-specific IT certification researchers with at least a decade of experience at Fortune 500 companies.

exam =32

Certified Information Security Manager (CISM) Practice Tests

Guarantee

Satisfaction Guaranteed

Pass4sure has a remarkable Isaca Candidate Success record. We're confident of our products and provide no hassle product exchange. That's how confident we are!

99.3% Pass Rate
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • exam =34
    Questions & Answers

    Questions & Answers

    1228 Questions

    $124.99
    exam =35
  • exam =37
    CISM Video Course

    Training Course

    388 Video Lectures

    $39.99
  • exam =36
    Study Guide

    Study Guide

    817 PDF Pages

    $29.99

Isaca CISM Practice Test 28

Question 270

A security manager is briefing business leadership, the team has started remediation after finding that the risk committee considers doing nothing about a minor, well-understood residual exposure. Which measurement would be most relevant for judging whether the exposure is reducing?

  1. Measure residual exposure following the chosen phased treatment.
  2. Measure residual likelihood and impact after implementation.
  3. Track accepted-risk expiry and trigger exceptions.
  4. Count acceptance decisions outside delegated limits.

Explanation

Correct Answer

C:

Track accepted-risk expiry and trigger exceptions. Risk acceptance is an accountable monitored choice, not neglect.

Incorrect Answers

A:

Risk response must balance business consequences and acceptable residual exposure. That is a different operating condition from “doing nothing about a minor, well-understood residual exposure”: “breach risk but contract termination would halt payroll”.

B:

Treatment should be proportionate and demonstrably effective. It serves “eliminates a common attack path”, not “doing nothing about a minor, well-understood residual exposure”.

D:

Only authorized decision-makers can accept the business consequence. That matters for “accept material exposure beyond the group's risk appetite” rather than the condition “doing nothing about a minor, well-understood residual exposure”.

Question 271

During a control and risk oversight meeting, a control owner claims remediation is complete following reports that the risk committee considers doing nothing about a minor, well-understood residual exposure. Which evidence would best substantiate whether the intended management outcome is actually achieved?

  1. Reassess the exposure when threat or control assumptions change.
  2. Check signed approvals against the enterprise risk appetite statement.
  3. Validate migration readiness and post-retirement exposure removal.
  4. Audit monitoring coverage and incident obligations against the contract.

Explanation

Correct Answer

A:

Reassess the exposure when threat or control assumptions change. Risk acceptance is an accountable monitored choice, not neglect.

Incorrect Answers

B:

Only authorized decision-makers can accept the business consequence. The boundary it addresses is “accept material exposure beyond the group's risk appetite”, while this case concerns “doing nothing about a minor, well-understood residual exposure”.

C:

Stopping a risky activity can remove the scenario entirely. This solves “by moving its service to a maintained platform”; the stated issue is “doing nothing about a minor, well-understood residual exposure”.

D:

Outsourcing activities does not transfer accountability for business risk. The deciding difference is “security monitoring but retains liability for customer breaches” versus “doing nothing about a minor, well-understood residual exposure”.

Question 272

In the next assurance review, executives are reviewing a material concern: The risk committee considers doing nothing about a minor, well-understood residual exposure. What should the security manager elevate when decision-makers review this matter?

  1. Report expected risk reduction against resource use.
  2. Report avoidance cost versus risk if continued.
  3. Report what residual harm remains after insurance purchase.
  4. Report why the accepted exposure remains within approved tolerance.

Explanation

Correct Answer

D:

Report why the accepted exposure remains within approved tolerance. Risk acceptance is an accountable monitored choice, not neglect.

Incorrect Answers

A:

Treatment should be proportionate and demonstrably effective. The deciding difference is “eliminates a common attack path” versus “doing nothing about a minor, well-understood residual exposure”.

B:

Stopping a risky activity can remove the scenario entirely. Its application is “by moving its service to a maintained platform”, not the need “doing nothing about a minor, well-understood residual exposure”.

C:

Risk transfer changes who pays, not whether incidents occur. That is a different operating condition from “doing nothing about a minor, well-understood residual exposure”: “an identified data exposure weakness”.

Question 273

During an enterprise security review, the team learns that a shared-service database handles records for four departments, with no risk owner. What management action should be prioritized to address this situation?

  1. Document both control operators and risk owners in the RACI matrix.
  2. Return the acceptance to a duly authorized sales risk owner.
  3. Specify retained internal incident accountability in the service operating model.
  4. Identify a senior business owner with authority over cross-unit consequences.

Explanation

Correct Answer

D:

Identify a senior business owner with authority over cross-unit consequences. The control implementer cannot automatically accept the enterprise risk.

Incorrect Answers

A:

Responsibility for control operation differs from ownership of business loss. It serves “ownership from the business processes relying on it”, not “records for four departments, with no risk owner”.

B:

Technical expertise informs decisions but does not confer business risk authority. The present requirement is “records for four departments, with no risk owner”; “form for a loss affecting the sales division” is a distinct situation.

C:

Provider responsibilities need an accountable enterprise interface. That matters for “incidents, but no internal function handles business escalation” rather than the condition “records for four departments, with no risk owner”.

Question 274

A security manager is briefing business leadership, risk ownership must be assigned after reports that a shared-service database handles records for four departments, with no risk owner. Which assignment provides appropriate accountability for the affected business risk?

  1. Make business managers accountable for acceptance and control teams responsible for operation.
  2. Assign enterprise service sponsorship and data-owner representation.
  3. Assign a business service owner and internal response coordinator.
  4. Make the business executive accountable for financial consequences.

Explanation

Correct Answer

B:

Assign enterprise service sponsorship and data-owner representation. The control implementer cannot automatically accept the enterprise risk.

Incorrect Answers

A:

Responsibility for control operation differs from ownership of business loss. The boundary it addresses is “ownership from the business processes relying on it”, while this case concerns “records for four departments, with no risk owner”.

C:

Provider responsibilities need an accountable enterprise interface. The deciding difference is “incidents, but no internal function handles business escalation” versus “records for four departments, with no risk owner”.

D:

Technical expertise informs decisions but does not confer business risk authority. Its application is “form for a loss affecting the sales division”, not the need “records for four departments, with no risk owner”.

Question 275

During a control and risk oversight meeting, the team has started remediation after finding that a shared-service database handles records for four departments, with no risk owner. Which measurement would be most relevant for judging whether the exposure is reducing?

  1. Track escalations without accountable internal recipients.
  2. Track risks without mapped control and business owners.
  3. Measure risk acceptances signed outside delegated authority.
  4. Track database risks lacking one accountable decision authority.

Explanation

Correct Answer

D:

Track database risks lacking one accountable decision authority. The control implementer cannot automatically accept the enterprise risk.

Incorrect Answers

A:

Provider responsibilities need an accountable enterprise interface. Its application is “incidents, but no internal function handles business escalation”, not the need “records for four departments, with no risk owner”.

B:

Responsibility for control operation differs from ownership of business loss. That is a different operating condition from “records for four departments, with no risk owner”: “ownership from the business processes relying on it”.

C:

Technical expertise informs decisions but does not confer business risk authority. It serves “form for a loss affecting the sales division”, not “records for four departments, with no risk owner”.

Question 276

In the next assurance review, a control owner claims remediation is complete following reports that a shared-service database handles records for four departments, with no risk owner. Which evidence would best substantiate whether the intended management outcome is actually achieved?

  1. Validate role assignments with walkthroughs of failed controls.
  2. Review contracts, playbooks, and sample incident handoffs.
  3. Audit the acceptance workflow and approval matrix.
  4. Review role matrix and acceptance signoffs for material database risks.

Explanation

Correct Answer

D:

Review role matrix and acceptance signoffs for material database risks. The control implementer cannot automatically accept the enterprise risk.

Incorrect Answers

A:

Responsibility for control operation differs from ownership of business loss. The present requirement is “records for four departments, with no risk owner”; “ownership from the business processes relying on it” is a distinct situation.

B:

Provider responsibilities need an accountable enterprise interface. That matters for “incidents, but no internal function handles business escalation” rather than the condition “records for four departments, with no risk owner”.

C:

Technical expertise informs decisions but does not confer business risk authority. The boundary it addresses is “form for a loss affecting the sales division”, while this case concerns “records for four departments, with no risk owner”.

Question 277

At the next enterprise governance checkpoint, executives are reviewing a material concern: A shared-service database handles records for four departments, with no risk owner. What should the security manager elevate when decision-makers review this matter?

  1. Report any gaps in who acts and who decides.
  2. Report invalid approvals and potential unowned exposure.
  3. Escalate conflicting risk ownership to executive governance.
  4. Report unmanaged escalation gaps and possible response delay.

Explanation

Correct Answer

C:

Escalate conflicting risk ownership to executive governance. The control implementer cannot automatically accept the enterprise risk.

Incorrect Answers

A:

Responsibility for control operation differs from ownership of business loss. This solves “ownership from the business processes relying on it”; the stated issue is “records for four departments, with no risk owner”.

B:

Technical expertise informs decisions but does not confer business risk authority. The deciding difference is “form for a loss affecting the sales division” versus “records for four departments, with no risk owner”.

D:

Provider responsibilities need an accountable enterprise interface. That is a different operating condition from “records for four departments, with no risk owner”: “incidents, but no internal function handles business escalation”.

Question 278

A security manager is briefing business leadership, the team learns that a security engineer signs a risk-acceptance form for a loss affecting the sales division. What management action should be prioritized to address this situation?

  1. Identify a senior business owner with authority over cross-unit consequences.
  2. Specify retained internal incident accountability in the service operating model.
  3. Document both control operators and risk owners in the RACI matrix.
  4. Return the acceptance to a duly authorized sales risk owner.

Explanation

Correct Answer

D:

Return the acceptance to a duly authorized sales risk owner. Technical expertise informs decisions but does not confer business risk authority.

Incorrect Answers

A:

The control implementer cannot automatically accept the enterprise risk. That is a different operating condition from “form for a loss affecting the sales division”: “records for four departments, with no risk owner”.

B:

Provider responsibilities need an accountable enterprise interface. It serves “incidents, but no internal function handles business escalation”, not “form for a loss affecting the sales division”.

C:

Responsibility for control operation differs from ownership of business loss. The present requirement is “form for a loss affecting the sales division”; “ownership from the business processes relying on it” is a distinct situation.

Question 279

During a control and risk oversight meeting, risk ownership must be assigned after reports that a security engineer signs a risk-acceptance form for a loss affecting the sales division. Which assignment provides appropriate accountability for the affected business risk?

  1. Make business managers accountable for acceptance and control teams responsible for operation.
  2. Assign enterprise service sponsorship and data-owner representation.
  3. Make the business executive accountable for financial consequences.
  4. Assign a business service owner and internal response coordinator.

Explanation

Correct Answer

C:

Make the business executive accountable for financial consequences. Technical expertise informs decisions but does not confer business risk authority.

Incorrect Answers

A:

Responsibility for control operation differs from ownership of business loss. That matters for “ownership from the business processes relying on it” rather than the condition “form for a loss affecting the sales division”.

B:

The control implementer cannot automatically accept the enterprise risk. The boundary it addresses is “records for four departments, with no risk owner”, while this case concerns “form for a loss affecting the sales division”.

D:

Provider responsibilities need an accountable enterprise interface. The deciding difference is “incidents, but no internal function handles business escalation” versus “form for a loss affecting the sales division”.

Question 280

In the next assurance review, the team has started remediation after finding that a security engineer signs a risk-acceptance form for a loss affecting the sales division. Which measurement would be most relevant for judging whether the exposure is reducing?

  1. Track escalations without accountable internal recipients.
  2. Measure risk acceptances signed outside delegated authority.
  3. Track database risks lacking one accountable decision authority.
  4. Track risks without mapped control and business owners.

Explanation

Correct Answer

B:

Measure risk acceptances signed outside delegated authority. Technical expertise informs decisions but does not confer business risk authority.

Incorrect Answers

A:

Provider responsibilities need an accountable enterprise interface. The deciding difference is “incidents, but no internal function handles business escalation” versus “form for a loss affecting the sales division”.

C:

The control implementer cannot automatically accept the enterprise risk. That is a different operating condition from “form for a loss affecting the sales division”: “records for four departments, with no risk owner”.

D:

Responsibility for control operation differs from ownership of business loss. It serves “ownership from the business processes relying on it”, not “form for a loss affecting the sales division”.