Question 330
For the case where a pulp mill adds an IIoT gateway after the system risk assessment is approved, what is the clearest acceptance check?
Explanation
Correct Answer
The evidence links the outcome to the security mechanism: risk assessment is revisited for material architecture changes. The corresponding design step is to reassess the new trust boundary and update the architecture before gateway commissioning.
Incorrect Answers
This check belongs to Risk treatment ownership. For the current issue, acceptance should establish that the updated inventory and risk register include the gateway's traffic and external peers.
This observation comes from Outage window tradeoff, a separate industrial condition. It does not prove the required result: the updated inventory and risk register include the gateway's traffic and external peers.
The stated evidence would be appropriate for Conduit consequence. This design instead needs to show that the updated inventory and risk register include the gateway's traffic and external peers.