Question 1030
Which recorded result would establish the control is working when a PLC accepts remote configuration from every Ethernet interface although only one maintenance path is required?
Explanation
Correct Answer
The acceptance result directly demonstrates the requirement has been met. The enabling measure is to disable or filter unnecessary configuration services and interfaces; minimum functionality includes reducing management reachability.
Incorrect Answers
This check belongs to Firmware provenance. For the current issue, acceptance should establish that authorized engineering access works only over the approved path.
The stated evidence would be appropriate for Secure switch management. This design instead needs to show that authorized engineering access works only over the approved path.
This observation comes from Locked cabinets, a separate industrial condition. It does not prove the required result: authorized engineering access works only over the approved path.