Question 1020
During an OT architecture review, a facility marks a high-risk unprotected command conduit as resolved after purchasing, not deploying, a firewall. What is the most targeted corrective approach?
Explanation
Correct Answer
Risk closure needs implemented and verified risk reduction. Confirm completion when the risk record links to the accepted firewall rule test results.
Incorrect Answers
Threat likelihood evidence is a separate issue; in this design, risk closure needs implemented and verified risk reduction.
This measure is useful for Temporary operations risk, where a maintenance bypass makes a process-control interlock temporarily accessible to a portable workstation. In the present case, procurement does not itself reduce exploitable exposure; the targeted response is different.
That step responds to Business service mapping, not the reported issue. Here the relevant design principle is that risk closure needs implemented and verified risk reduction.