Question 600
At Ashfield Utilities, a vulnerability list ranks a safety-related PLC below a low-impact workstation because their severity scores differ. The relevant endpoint is remote pumping station P-36; the response has to preserve an approved emergency operations path. What is the most defensible architecture or policy decision?
Explanation
Correct Answer
Industrial risk prioritization requires likelihood and operational consequence; CVSS alone is not a plant-safety impact model. The mitigation applies to remote pumping station P-36; review a sample of ranked assets and confirm documented exposure path, process impact, decision owner and mitigation plan.
Incorrect Answers
Sort all fixes by CVSS only, disregarding safety function and maintenance windows does not establish the specified technical control at Ashfield Utilities. Industrial risk prioritization requires likelihood and operational consequence; CVSS alone is not a plant-safety impact model. The pilot needs observable evidence: Review a sample of ranked assets and confirm documented exposure path, process impact, decision owner and mitigation plan.
Set risk equal to the number of signatures installed on a firewall. is an unsuitable substitution for the required control. For remote pumping station P-36, the measurable acceptance standard is: Review a sample of ranked assets and confirm documented exposure path, process impact, decision owner and mitigation plan.
Treat isolated devices as risk free without confirming actual conduit exposure bypasses a case-specific safeguard rather than satisfying it. Industrial risk prioritization requires likelihood and operational consequence; CVSS alone is not a plant-safety impact model. Review the planned action: Combine vulnerability severity with reachability, process consequence, compensating controls and asset ownership in the OT risk register.