mcAfee Secure Website
exam =5
exam =6

Exam Code: CCP

Exam Name: Certified CMMC Professional

Certification Provider: Cyber AB

Corresponding Certification: Certified CMMC Professional

Cyber AB CCP Questions & Answers

Reliable & Actual Study Materials for CCP Exam Success

201 Questions & Answers with Testing Engine

"CCP: Certified CMMC Professional" Testing Engine covers all the knowledge points of the real Cyber AB CCP exam.

The latest actual CCP Questions & Answers from Pass4sure. Everything you need to prepare and get best score at CCP exam easily and quickly.

exam =7
Guarantee

Satisfaction Guaranteed

Pass4sure has a remarkable Cyber AB Candidate Success record. We're confident of our products and provide no hassle product exchange. That's how confident we are!

99.3% Pass Rate
Was: $137.49
Now: $124.99

Cyber AB CCP Practice Test 10

Question 90

At Pine Harbor Analytics, an assessment report includes raw CUI screenshots in an unrestricted shared download folder. The review team must protect the integrity of any information it handles and stay within its authorized CMMC role. Which action is most appropriate as the immediate next step for this issue?

  1. Send a public link to ensure everyone can review the findings.
  2. Assume removing a report title eliminates all CUI risk.
  3. Restrict report artifacts to authorized handling and distribution paths.
  4. Place the archive on personal removable storage without controls.

Explanation

Correct Answer

C:

Assessment reporting and archival duties include safeguarding sensitive source evidence. Validate by checking: Verify access restrictions and approved retention and distribution decisions.

Incorrect Answers

A:

For Pine Harbor Analytics, “Send a public link to ensure everyone can review the findings” is not sufficient to establish the required control. The applicable action is Restrict report artifacts to authorized handling and distribution paths.

B:

Assessment reporting and archival duties include safeguarding sensitive source evidence.

D:

Verify this with: Verify access restrictions and approved retention and distribution decisions.

Question 91

At Aspen Tech Components, a malware scanner is installed but its protection signatures have not been refreshed for a year. The review team must protect the integrity of any information it handles and stay within its authorized CMMC role. Which action is most appropriate as the immediate next step for this issue?

  1. Configure regular updates and verify current malicious-code protection mechanisms.
  2. Disable definitions so old detections cannot interrupt work.
  3. Assume a successful login proves protection content is current.
  4. Replace the update schedule with a monthly marketing newsletter.

Explanation

Correct Answer

A:

Detection capabilities require current definitions or equivalent protection updates to remain effective. Validate by checking: Inspect actual protection update timestamps and test agent reporting.

Incorrect Answers

B:

For Aspen Tech Components, “Disable definitions so old detections cannot interrupt work” is not sufficient to establish the required control. The applicable action is Configure regular updates and verify current malicious-code protection mechanisms.

C:

Detection capabilities require current definitions or equivalent protection updates to remain effective.

D:

Verify this with: Inspect actual protection update timestamps and test agent reporting.

Question 92

At Ridgeway Aerospace, a CCP is deciding whether to use an organization marketing deck or the official CMMC Level 1 Assessment Guide to review a Level 1 practice. The review team must protect the integrity of any information it handles and stay within its authorized CMMC role. Which action is most appropriate as the immediate next step for this issue?

  1. Use the supplier's pitch deck as the mandatory assessment scoring guide.
  2. Assume a general training slide is legally superior to current regulatory text.
  3. Treat the latest press release as a complete list of assessment objectives.
  4. Use the current official Level 1 assessment guide and associated practice objectives.

Explanation

Correct Answer

D:

Published assessment guidance provides the objectives and methods for reviewing the applicable practice. Validate by checking: Record the guide revision and practice objectives used in the review.

Incorrect Answers

A:

For Ridgeway Aerospace, “Use the supplier's pitch deck as the mandatory assessment scoring guide” is not sufficient to establish the required control. The applicable action is Use the current official Level 1 assessment guide and associated practice objectives.

B:

Published assessment guidance provides the objectives and methods for reviewing the applicable practice.

C:

Verify this with: Record the guide revision and practice objectives used in the review.

Question 93

At Windham Aviation, a procurement portal receives FCI contract schedules but the scope excludes it because it does not directly store CUI. The review team must protect the integrity of any information it handles and stay within its authorized CMMC role. Which action is most appropriate as the immediate next step for this issue?

  1. Trace FCI processing and evaluate the portal under the applicable Level 1 assessment scope.
  2. Exclude a system solely because it lacks an official CUI banner.
  3. Require every public website to be treated as a CUI asset without dataflow review.
  4. Use cloud region selection alone to determine whether FCI exists.

Explanation

Correct Answer

A:

Level 1 FCI scope is not limited to CUI systems; FCI processing matters independently. Validate by checking: Document FCI fields, affected portal systems and relevant safeguards.

Incorrect Answers

B:

For Windham Aviation, “Exclude a system solely because it lacks an official CUI banner” is not sufficient to establish the required control. The applicable action is Trace FCI processing and evaluate the portal under the applicable Level 1 assessment scope.

C:

Level 1 FCI scope is not limited to CUI systems; FCI processing matters independently.

D:

Verify this with: Document FCI fields, affected portal systems and relevant safeguards.

Question 94

At Redstone Research, a contractor's office network has an internet path into the internal FCI segment without a defined protection boundary. The review team must protect the integrity of any information it handles and stay within its authorized CMMC role. Which action is most appropriate as the immediate next step for this issue?

  1. Assume a public-facing website certificate alone is enough segmentation.
  2. Remove firewall rules so monitoring tools can reach all addresses.
  3. Implement and verify appropriate communications boundary protection between public and internal resources.
  4. Depend only on a physical door lock to secure network flows.

Explanation

Correct Answer

C:

Network boundary controls limit unauthorized information flow and exposure. Validate by checking: Inspect enforced boundary rules and test unauthorized inbound traffic denial.

Incorrect Answers

A:

For Redstone Research, “Assume a public-facing website certificate alone is enough segmentation” is not sufficient to establish the required control. The applicable action is Implement and verify appropriate communications boundary protection between public and internal resources.

B:

Network boundary controls limit unauthorized information flow and exposure.

D:

Verify this with: Inspect enforced boundary rules and test unauthorized inbound traffic denial.

Question 95

At Quarryline Fabrication, an engineer presents a cloud provider's general certification as proof the contractor configured all its CUI permissions correctly. The review team must protect the integrity of any information it handles and stay within its authorized CMMC role. Which action is most appropriate as the immediate next step for this issue?

  1. Treat every inherited cloud control as covering every customer practice.
  2. Evaluate the contractor's applicable shared-responsibility controls and actual tenant configuration.
  3. Require the provider to make the contractor's personnel authorization decisions.
  4. Exclude all cloud resources solely because the vendor has a security certificate.

Explanation

Correct Answer

B:

A provider's assurance does not automatically prove customer-owned access settings or implementation. Validate by checking: Review service boundary, control allocation and customer-side effective permissions.

Incorrect Answers

A:

For Quarryline Fabrication, “Treat every inherited cloud control as covering every customer practice” is not sufficient to establish the required control. The applicable action is Evaluate the contractor's applicable shared-responsibility controls and actual tenant configuration.

C:

A provider's assurance does not automatically prove customer-owned access settings or implementation.

D:

Verify this with: Review service boundary, control allocation and customer-side effective permissions.

Question 96

At Windham Aviation, an assessment coordinator has not assigned responsible interview contacts or identified the systems that will be observed. The review team must protect the integrity of any information it handles and stay within its authorized CMMC role. Which action is most appropriate as the immediate next step for this issue?

  1. Let each examiner contact random employees without an agreed plan.
  2. Use only a marketing timeline instead of a controlled work plan.
  3. Complete the assessment plan with owners, objectives, methods, resources and schedule.
  4. Begin collecting all corporate records unrelated to CMMC objectives.

Explanation

Correct Answer

C:

A clear plan enables consistent, authorized evidence collection and reduces scope confusion. Validate by checking: Check a complete authorized assessment plan against the agreed objectives and scope.

Incorrect Answers

A:

For Windham Aviation, “Let each examiner contact random employees without an agreed plan” is not sufficient to establish the required control. The applicable action is Complete the assessment plan with owners, objectives, methods, resources and schedule.

B:

A clear plan enables consistent, authorized evidence collection and reduces scope confusion.

D:

Verify this with: Check a complete authorized assessment plan against the agreed objectives and scope.

Question 97

At Redstone Research, a team says that a subcontractor has no safeguarding responsibilities because a prime contractor supplied the CUI. The review team must protect the integrity of any information it handles and stay within its authorized CMMC role. Which action is most appropriate as the immediate next step for this issue?

  1. Assume the prime contractor's certificate covers every downstream environment automatically.
  2. Ignore the controls until the subcontractor applies for its own CMMC badge.
  3. Use a shared consumer file-transfer account without recipient safeguards.
  4. Review the subcontract and applicable flow-down clauses before assigning data protection responsibilities.

Explanation

Correct Answer

D:

Responsibilities follow legal and contractual handling requirements, not merely the identity of the data sender. Validate by checking: Trace the CUI path, contract clauses and subcontractor obligations.

Incorrect Answers

A:

For Redstone Research, “Assume the prime contractor's certificate covers every downstream environment automatically” is not sufficient to establish the required control. The applicable action is Review the subcontract and applicable flow-down clauses before assigning data protection responsibilities.

B:

Responsibilities follow legal and contractual handling requirements, not merely the identity of the data sender.

C:

Verify this with: Trace the CUI path, contract clauses and subcontractor obligations.

Question 98

At Clearview Supply, a federal supplier's endpoints never scan downloaded files or externally attached storage for malware. The review team must protect the integrity of any information it handles and stay within its authorized CMMC role. Which action is most appropriate as the immediate next step for this issue?

  1. Enable suitable periodic and real-time scanning of files from external sources as applicable.
  2. Disable removable-media protections because users need convenience.
  3. Rely solely on a building's physical security camera.
  4. Classify every file as safe after renaming its extension.

Explanation

Correct Answer

A:

System and file scanning helps detect malicious content at relevant entry points. Validate by checking: Confirm configured scanning activity and sampled controlled-file inspection evidence.

Incorrect Answers

B:

For Clearview Supply, “Disable removable-media protections because users need convenience” is not sufficient to establish the required control. The applicable action is Enable suitable periodic and real-time scanning of files from external sources as applicable.

C:

System and file scanning helps detect malicious content at relevant entry points.

D:

Verify this with: Confirm configured scanning activity and sampled controlled-file inspection evidence.

Question 99

At Holloway Precision, a supplier's facilities team provides building access controls for the enclave but is absent from the planned assessment interviews. The review team must protect the integrity of any information it handles and stay within its authorized CMMC role. Which action is most appropriate as the immediate next step for this issue?

  1. Assume a physical protection practice never involves facilities staff.
  2. Include supporting people, processes and facilities where they affect scoped requirements.
  3. Exclude a necessary supporting unit solely because it is a different cost center.
  4. Review only cloud network logs for all physical protection objectives.

Explanation

Correct Answer

B:

Organizational scoping must cover relevant support functions, not only the central IT team. Validate by checking: Show the responsibilities and evidence sources for relevant physical access safeguards.

Incorrect Answers

A:

For Holloway Precision, “Assume a physical protection practice never involves facilities staff” is not sufficient to establish the required control. The applicable action is Include supporting people, processes and facilities where they affect scoped requirements.

C:

Organizational scoping must cover relevant support functions, not only the central IT team.

D:

Verify this with: Show the responsibilities and evidence sources for relevant physical access safeguards.

Question 100

At Briarfield Defense, a supplier seeks final certification solely because its POA&M spreadsheet has dates filled in. The review team must protect the integrity of any information it handles and stay within its authorized CMMC role. Which action is most appropriate as the immediate next step for this issue?

  1. Distinguish documented corrective plans from verified completion and formal status determination.
  2. Issue a final certificate when the spreadsheet has no blank cells.
  3. Mark unmet practices met automatically when a remediation owner is named.
  4. Skip the required post-remediation validation process.

Explanation

Correct Answer

A:

POA&M tracking alone is not equivalent to an authorized assessment outcome. Validate by checking: Review actual technical closure evidence and the applicable assessor decision.

Incorrect Answers

B:

For Briarfield Defense, “Issue a final certificate when the spreadsheet has no blank cells” is not sufficient to establish the required control. The applicable action is Distinguish documented corrective plans from verified completion and formal status determination.

C:

POA&M tracking alone is not equivalent to an authorized assessment outcome.

D:

Verify this with: Review actual technical closure evidence and the applicable assessor decision.