Question 730
Colocation site RMA handoff. Field report: Support requests a baseline before a chassis replacement. A colleague proposes: “Delete the old configuration as a first evidence-gathering step.” Which technical assessment is best supported?
Explanation
Correct Answer
The alternative does not address the actual reported dependency. A multi-part prechange baseline supports restoration and meaningful postchange comparison. The supported intervention is collect approved configuration, interface, version, inventory and logs before shutdown; acceptance should show that baseline evidence is time-stamped and tied to the old device ID.
Incorrect Answers
It assumes an unrelated action establishes service recovery. Nothing about “Rely on a memory of last week's link state” demonstrates whether baseline evidence is time-stamped and tied to the old device ID.
The failure described in the field report requires a functional check that baseline evidence is time-stamped and tied to the old device ID.
The proposed step “Capture only the new chassis model name after the swap” is not the required mechanism.