exam =5
exam =6

Exam Code: 800-150

Exam Name: Supporting Cisco Devices for Field Technicians

Certification Provider: Cisco

Cisco 800-150 Questions & Answers

Reliable & Actual Study Materials for 800-150 Exam Success

100 Questions & Answers with Testing Engine

"800-150: Supporting Cisco Devices for Field Technicians" Testing Engine covers all the knowledge points of the real Cisco 800-150 exam.

The latest actual 800-150 Questions & Answers from Pass4sure. Everything you need to prepare and get best score at 800-150 exam easily and quickly.

exam =7
Guarantee

Satisfaction Guaranteed

Pass4sure has a remarkable Cisco Candidate Success record. We're confident of our products and provide no hassle product exchange. That's how confident we are!

99.3% Pass Rate
Was: $137.49
Now: $124.99

Cisco 800-150 Practice Test 22

Question 210

Headquarters wiring-closet visit. Field report: A router has a connected IPv4 route but cannot deliver traffic to a local next hop. The shift lead must choose a return-to-service note for this ticket. Which handoff is technically adequate?

  1. Perform or retain the approved action: check arp resolution and layer 2 adjacency for that next hop; document evidence that the correct next-hop MAC appears and packets leave the intended interface.
  2. Apply “Swap an unrelated BGP community attribute” as a substitute and declare success from shipment receipt alone.
  3. Defer service verification after “Use ICMP TTL values as hardware addresses” until the next reported incident.
  4. Close after recording “Enable DNS recursion on the router to populate its ARP cache” without checking that the correct next-hop MAC appears and packets leave the intended interface.

Explanation

Correct Answer

A:

This handoff preserves the required corrective action and the verifiable service outcome. A connected IPv4 next hop still requires valid local Layer 2 resolution. Recording that the correct next-hop MAC appears and packets leave the intended interface makes the signoff testable.

Incorrect Answers

B:

Delivery paperwork describes logistics, not recovered functionality. “Swap an unrelated BGP community attribute” leaves the technical requirement and its validation unresolved.

C:

A future incident is not a reasonable acceptance gate for a known problem. “Use ICMP TTL values as hardware addresses” is not evidence that the correct next-hop MAC appears and packets leave the intended interface.

D:

This proposes a different action with no acceptance evidence. “Enable DNS recursion on the router to populate its ARP cache” cannot replace the validated measure that the correct next-hop MAC appears and packets leave the intended interface.

Question 211

Colocation site RMA handoff. Field report: A new router has no management address and requires local CLI access. A colleague proposes: “Expect an Ethernet access cable to present console text without terminal service.” Which technical assessment is best supported?

  1. The proposed shortcut is sufficient because use a public http url as a substitute for console electrical signaling.
  2. The proposal overlooks the reported dependency: Console access uses a designated physical or USB console connection and terminal session.
  3. The original problem can be treated as resolved from inventory labels alone, without checking console access serial behavior.
  4. There is no need to validate the reported dependency once change the switch mac table to produce boot text on the laptop.

Explanation

Correct Answer

B:

The alternative does not address the actual reported dependency. Console access uses a designated physical or USB console connection and terminal session. The supported intervention is connect via its supported console port, adapter and terminal settings; acceptance should show that boot output and a login prompt are visible on the correct console.

Incorrect Answers

A:

The proposed step “Use a public HTTP URL as a substitute for console electrical signaling” is not the required mechanism.

C:

The failure described in the field report requires a functional check that boot output and a login prompt are visible on the correct console.

D:

It assumes an unrelated action establishes service recovery. Nothing about “Change the switch MAC table to produce boot text on the laptop” demonstrates whether boot output and a login prompt are visible on the correct console.

Question 212

Remote office replacement window. Field report: A server consolidation project needs a layer to host and schedule guest virtual machines. A colleague proposes: “Deploy a Fibre Channel zoning rule as a CPU scheduler.” Which technical assessment is best supported?

  1. The proposed shortcut is sufficient because use a layer 2 ethernet patch panel as a virtual machine monitor.
  2. There is no need to validate the reported dependency once assign a dns entry to allocate hypervisor memory.
  3. The proposal overlooks the reported dependency: A hypervisor abstracts host compute resources for virtual machines.
  4. The original problem can be treated as resolved from inventory labels alone, without checking hypervisor role behavior.

Explanation

Correct Answer

C:

The alternative does not address the actual reported dependency. A hypervisor abstracts host compute resources for virtual machines. The supported intervention is select a supported hypervisor for compute virtualization; acceptance should show that guest instances run and have their allocated resources.

Incorrect Answers

A:

The proposed step “Use a layer 2 Ethernet patch panel as a virtual machine monitor” is not the required mechanism.

B:

It assumes an unrelated action establishes service recovery. Nothing about “Assign a DNS entry to allocate hypervisor memory” demonstrates whether guest instances run and have their allocated resources.

D:

The failure described in the field report requires a functional check that guest instances run and have their allocated resources.

Question 213

Disaster-recovery facility inspection. Field report: A damaged meeting-room video endpoint is swapped after documented asset approval. A colleague proposes: “Use a campus routing table as the only saved endpoint configuration.” Which technical assessment is best supported?

  1. There is no need to validate the reported dependency once disable all meeting services until the new model is retired.
  2. The original problem can be treated as resolved from inventory labels alone, without checking video endpoint replacement behavior.
  3. The proposed shortcut is sufficient because treat an optical link led as proof of working microphones and camera.
  4. The proposal overlooks the reported dependency: Video endpoint recovery includes provisioning and media components, not just electrical power.

Explanation

Correct Answer

D:

The alternative does not address the actual reported dependency. Video endpoint recovery includes provisioning and media components, not just electrical power. The supported intervention is restore supported room configuration, registration and meeting-media tests; acceptance should show that room call control, video, microphone and speaker paths operate.

Incorrect Answers

A:

It assumes an unrelated action establishes service recovery. Nothing about “Disable all meeting services until the new model is retired” demonstrates whether room call control, video, microphone and speaker paths operate.

B:

The failure described in the field report requires a functional check that room call control, video, microphone and speaker paths operate.

C:

The proposed step “Treat an optical link LED as proof of working microphones and camera” is not the required mechanism.

Question 214

Main campus hardware-service ticket. Field report: A replacement E-Series module powers on but the hosted branch application is unreachable. The shift lead must choose a return-to-service note for this ticket. Which handoff is technically adequate?

  1. Perform or retain the approved action: check module management, guest network and application start state; document evidence that the hosted application is reachable through its intended segment.
  2. Apply “Assume module power LEDs prove guest services are operational” as a substitute and declare success from shipment receipt alone.
  3. Defer service verification after “Reset other branch routers to fix local module guest networking” until the next reported incident.
  4. Close after recording “Change the WAN router hostname as the entire compute restoration” without checking that the hosted application is reachable through its intended segment.

Explanation

Correct Answer

A:

This handoff preserves the required corrective action and the verifiable service outcome. Compute module availability, network access and hosted application service are separate acceptance steps. Recording that the hosted application is reachable through its intended segment makes the signoff testable.

Incorrect Answers

B:

Delivery paperwork describes logistics, not recovered functionality. “Assume module power LEDs prove guest services are operational” leaves the technical requirement and its validation unresolved.

C:

A future incident is not a reasonable acceptance gate for a known problem. “Reset other branch routers to fix local module guest networking” is not evidence that the hosted application is reachable through its intended segment.

D:

This proposes a different action with no acceptance evidence. “Change the WAN router hostname as the entire compute restoration” cannot replace the validated measure that the hosted application is reachable through its intended segment.

Question 215

Regional north-campus service window. Field report: A newly attached AP cycles power while a switch power budget warning appears. The approved intervention is complete. What observation provides the strongest technical acceptance evidence?

  1. Confirm only that the work ticket says “completed,” without testing poe budget.
  2. Demonstrate that the switch reports allocated power within budget and the endpoint stays up.
  3. Confirm the site inventory list still contains the hostname, without validating the reported service.
  4. Confirm only that the technician attempted: apply a shorter dhcp lease as a poe repair.

Explanation

Correct Answer

B:

The switch reports allocated power within budget and the endpoint stays up. Insufficient PoE power can prevent attached endpoints from remaining online.

Incorrect Answers

A:

Check whether the switch reports allocated power within budget and the endpoint stays up.

C:

Confirm that the switch reports allocated power within budget and the endpoint stays up.

D:

For example, “Apply a shorter DHCP lease as a PoE repair” does not demonstrate the corrected technical state.

Question 216

Customer branch-site maintenance. Field report: The spare must match a ticket's PID and serial number. Which action is the most defensible first step?

  1. Trust the hostname as the unique chassis serial number.
  2. Use the interface description field as manufacturer PID evidence.
  3. Capture `show inventory` and compare to physical and RMA labels.
  4. Infer the serial number from the connected VLAN ID.

Explanation

Correct Answer

C:

Cisco inventory output exposes product and serial identifiers for chassis and FRUs. The action should lead to evidence that chassis PID, serial and relevant module identities match the replacement ticket.

Incorrect Answers

A:

This alternative would not solve the reported problem. Cisco inventory output exposes product and serial identifiers for chassis and FRUs. The field team must instead establish whether chassis PID, serial and relevant module identities match the replacement ticket.

B:

That change addresses a different aspect of the environment and leaves this requirement unresolved: the spare must match a ticket's pid and serial number. The relevant control is capture `show inventory` and compare to physical and rma labels.

D:

Attempting this shortcut is not an adequate substitute for the required action. Cisco inventory output exposes product and serial identifiers for chassis and FRUs. Post-change evidence is still needed.

Question 217

Primary data-center night shift. Field report: A Meraki replacement switch forwards locally but is not checking in to dashboard. Which action is the most defensible first step?

  1. Factory reset cloud credentials without reviewing the approved network path.
  2. Use SSH to a Cisco IOS router as the entire Meraki dashboard test.
  3. Assume local user traffic proves cloud control connectivity.
  4. Check management VLAN, addressing, DNS and outbound cloud connectivity.

Explanation

Correct Answer

D:

Cloud-managed device status depends on reachable management services and policy. The action should lead to evidence that the dashboard reports the correct replacement as online.

Incorrect Answers

A:

Attempting this shortcut is not an adequate substitute for the required action. Cloud-managed device status depends on reachable management services and policy. Post-change evidence is still needed.

B:

That change addresses a different aspect of the environment and leaves this requirement unresolved: a meraki replacement switch forwards locally but is not checking in to dashboard. The relevant control is check management vlan, addressing, dns and outbound cloud connectivity.

C:

This alternative would not solve the reported problem. Cloud-managed device status depends on reachable management services and policy. The field team must instead establish whether the dashboard reports the correct replacement as online.

Question 218

Headquarters wiring-closet visit. Field report: Call signaling succeeds but one-way audio occurs on a new branch path. The shift lead must choose a return-to-service note for this ticket. Which handoff is technically adequate?

  1. Perform or retain the approved action: test rtp/media routing and policy separately from call setup signaling; document evidence that real-time media packets and two-way speech across the intended path.
  2. Close after recording “Assume successful SIP registration proves bidirectional RTP” without checking that real-time media packets and two-way speech across the intended path.
  3. Apply “Change only the phone's display name to repair all audio streams” as a substitute and declare success from shipment receipt alone.
  4. Defer service verification after “Replace the power supply even though the handset remains powered” until the next reported incident.

Explanation

Correct Answer

A:

This handoff preserves the required corrective action and the verifiable service outcome. Call signaling and voice media are distinct flows with different path and filtering requirements. Recording that real-time media packets and two-way speech across the intended path makes the signoff testable.

Incorrect Answers

B:

This proposes a different action with no acceptance evidence. “Assume successful SIP registration proves bidirectional RTP” cannot replace the validated measure that real-time media packets and two-way speech across the intended path.

C:

Delivery paperwork describes logistics, not recovered functionality. “Change only the phone's display name to repair all audio streams” leaves the technical requirement and its validation unresolved.

D:

A future incident is not a reasonable acceptance gate for a known problem. “Replace the power supply even though the handset remains powered” is not evidence that real-time media packets and two-way speech across the intended path.

Question 219

Colocation site RMA handoff. Field report: The ticket lists a user's laptop and desk phone and asks which is a collaboration endpoint. A colleague proposes: “Classify the user laptop as a Fibre Channel SAN director.” Which technical assessment is best supported?

  1. The original problem can be treated as resolved from inventory labels alone, without checking endpoint identity behavior.
  2. The proposal overlooks the reported dependency: Collaboration endpoints include phones and video terminals that participate in calls.
  3. There is no need to validate the reported dependency once use a power distribution unit as an ip conferencing endpoint.
  4. The proposed shortcut is sufficient because treat a management switch as a video handset.

Explanation

Correct Answer

B:

The alternative does not address the actual reported dependency. Collaboration endpoints include phones and video terminals that participate in calls. The supported intervention is identify the ip phone and its call-control dependency; acceptance should show that the identified handset or video unit registers to the appropriate service.

Incorrect Answers

A:

The failure described in the field report requires a functional check that the identified handset or video unit registers to the appropriate service.

C:

It assumes an unrelated action establishes service recovery. Nothing about “Use a power distribution unit as an IP conferencing endpoint” demonstrates whether the identified handset or video unit registers to the appropriate service.

D:

The proposed step “Treat a management switch as a video handset” is not the required mechanism.

Question 220

Remote office replacement window. Field report: A compute blade replacement ticket refers to a server inside a shared UCS chassis. The shift lead must choose a return-to-service note for this ticket. Which handoff is technically adequate?

  1. Close after recording “Treat the blade as a standalone rack router with unrelated interface labels” without checking that the exact blade slot and compatible replacement are identified.
  2. Defer service verification after “Use an office access VLAN ID as the blade serial number” until the next reported incident.
  3. Perform or retain the approved action: locate chassis, slot, blade type and fabric path before swapping; document evidence that the exact blade slot and compatible replacement are identified.
  4. Apply “Unplug all chassis IOM links without checking redundancy” as a substitute and declare success from shipment receipt alone.

Explanation

Correct Answer

C:

This handoff preserves the required corrective action and the verifiable service outcome. Blade identity and connectivity are tied to chassis resources and fabric modules. Recording that the exact blade slot and compatible replacement are identified makes the signoff testable.

Incorrect Answers

A:

This proposes a different action with no acceptance evidence. “Treat the blade as a standalone rack router with unrelated interface labels” cannot replace the validated measure that the exact blade slot and compatible replacement are identified.

B:

A future incident is not a reasonable acceptance gate for a known problem. “Use an office access VLAN ID as the blade serial number” is not evidence that the exact blade slot and compatible replacement are identified.

D:

Delivery paperwork describes logistics, not recovered functionality. “Unplug all chassis IOM links without checking redundancy” leaves the technical requirement and its validation unresolved.

Supporting Cisco Devices for Field Technicians (800-150) Practice Tests