Question 490
During acceptance of a proposed enterprise topology, the reviewers observe: A national enterprise sends every configuration backup and log to one management collector in a single data center with no alternate destination. Which acceptance result best proves the design meets its requirement?
Explanation
Correct Answer
This directly validates management network service redundancy: Central monitoring infrastructure can become a single point of failure even when individual access devices have redundant uplinks. The linked design intervention is: Design appropriate collector and transport redundancy with supported failover and secure retention behavior. Results concerning another subsystem do not prove this requirement.
Incorrect Answers
Overly aggressive polling can consume limited control-plane CPU and management bandwidth without improving decision quality. “Select telemetry collection intervals and methods proportional to observed change rates and device capacity” would remedy that alternative situation, but it would not correct the present issue: central monitoring infrastructure can become a single point of failure even when individual access devices have redundant uplinks.
“Design correct multicast reverse paths and compatible unicast routing so upstream interfaces pass the RPF check” is the supported response when multicast RPF typically checks the route back toward the source or RP, not merely whether a receiver destination is reachable. Here the decisive response is “Design appropriate collector and transport redundancy with supported failover and secure retention behavior”, so that different intervention does not meet the stated requirement.
Uncoordinated system clocks undermine log chronology, audit correlation and incident reconstruction. “Use resilient approved NTP sources with authenticated or trusted network delivery where supported” applies to that other condition. The reported evidence is a national enterprise sends every configuration backup and log to one management collector in a single data center with no alternate destination; this alternative would address the wrong dependency.