Question 480
This statement is proposed during an architecture review: “Two tasks scheduled at the same time always execute in the intended order.” The observed condition is: An ETL workflow runs transformations before ingestion completes because its tasks are scheduled independently. Which principle should guide the design?
Explanation
Correct Answer
Define a supported task graph or dependency-aware orchestration that waits for upstream success. Downstream transformations start only after required upstream steps succeed.
Incorrect Answers
Measure throughput and tune compute, orchestration or incremental processing to bound lag. Downstream transformations start only after required upstream steps succeed.
Design an idempotent MERGE or deduplication strategy with explicit keys and retry tests. Task order must reflect data dependencies, not just the clock.
Align transformation refresh design with actual arrival frequency and consumer SLA. Downstream transformations start only after required upstream steps succeed.