Question 850
An implementation workbook lists capacity consolidation but omits how a data evacuation failure should affect the schedule. Site acceptance governance review: An approval board needs the evidence, proposed action and a testable success criterion. Which change-plan summary is the MOST decision-ready?
Explanation
Correct Answer
This is the controlled correction: Diagnostic evidence: Check expected evacuation progress signals, vendor stop conditions and support escalation ownership. Approved corrective scope: Add progress thresholds, a safe rollback or pause point and rescheduling criteria to the workplan. Acceptance: The plan records a decision path for incomplete evacuation and subsequent site visit needs. The packet connects the observed risk, the exact correction and an independently measurable gate. In this implementation case, An implementation workbook lists capacity consolidation but omits how a data evacuation failure should affect the schedule.
Incorrect Answers
This alternative proposes: Base approval on this unrelated alternative alone: Validate host login permissions but leave the data movement failure plan blank. This alternative plan is based on an adjacent issue rather than the controlling risk. In this implementation case, An implementation workbook lists capacity consolidation but omits how a data evacuation failure should affect the schedule.
This alternative proposes: Remove the source shelf anyway to preserve the contractual service date. A change board should not approve a step that deliberately bypasses required safeguards. In this implementation case, An implementation workbook lists capacity consolidation but omits how a data evacuation failure should affect the schedule.
This alternative proposes: Approve only the implementation step, with no root-cause evidence or defined acceptance: Add progress thresholds, a safe rollback or pause point and rescheduling criteria to the workplan. A proposal with a remedial command but no evidence or acceptance gate is not decision-ready. In this implementation case, An implementation workbook lists capacity consolidation but omits how a data evacuation failure should affect the schedule.