Question 710
A software NDU plan includes a forced failover but lacks application owner approval for tolerable transient path changes. Deployment evidence assessment: An approval board needs the evidence, proposed action and a testable success criterion. Which change-plan summary is the MOST decision-ready?
Explanation
Correct Answer
This is the controlled correction: Diagnostic evidence: Assess host multipathing resiliency, planned failover steps and affected service SLA gates. Approved corrective scope: Coordinate and obtain approval for a tested supported failover sequence before software maintenance. Acceptance: Application path monitoring and both controllers meet named acceptance thresholds after failover. The packet connects the observed risk, the exact correction and an independently measurable gate. In this implementation case, A software NDU plan includes a forced failover but lacks application owner approval for tolerable transient path changes.
Incorrect Answers
This alternative proposes: Base approval on this unrelated alternative alone: Review warranty serial numbers rather than service tolerance for the failover. This alternative plan is based on an adjacent issue rather than the controlling risk. In this implementation case, A software NDU plan includes a forced failover but lacks application owner approval for tolerable transient path changes.
This alternative proposes: Initiate an unannounced controller transition because storage health is green. A change board should not approve a step that deliberately bypasses required safeguards. In this implementation case, A software NDU plan includes a forced failover but lacks application owner approval for tolerable transient path changes.
This alternative proposes: Approve only the implementation step, with no root-cause evidence or defined acceptance: Coordinate and obtain approval for a tested supported failover sequence before software maintenance. A proposal with a remedial command but no evidence or acceptance gate is not decision-ready. In this implementation case, A software NDU plan includes a forced failover but lacks application owner approval for tolerable transient path changes.