Question 490
A project proposes the shortcut “Delete high-volume events to make charts look better” to handle this situation: A security operations manager sees high threat volume but no measurement of whether tuning reduced actual risky sessions. Which alternative should the engineer recommend instead?
Explanation
Correct Answer
Use posture and log evidence to evaluate control effectiveness and adjust policies with change control. Unlike the proposed shortcut, this addresses the cause and can be verified by testing: Before-and-after analysis shows relevant high-risk traffic is appropriately controlled without unjustified business disruption.
Incorrect Answers
A checklist or project output is not a direct test of enforcement—for example, the dashboard has fewer alert tiles. The acceptance check must confirm: use posture and log evidence to evaluate control effectiveness and adjust policies with change control.
Apply unreviewed any-any rules to reduce false positives. This records an intermediate task without proving the policy works; it leaves the original weakness unresolved: A security operations manager sees high threat volume but no measurement of whether tuning reduced actual risky sessions.
A configuration or meeting record is not the same as an observed control outcome. The proposed item—treat total log storage as the main security performance indicator—does not directly verify the requested control outcome.