Question 610
A portfolio council's prior approval included a budget condition that a program now wants to ignore. The governance charter and delegated authority limits must be respected. Which proposed shortcut should the portfolio manager REJECT as the LEAST defensible?
Explanation
Correct Answer
The shortcut to reject is: Remove the budget condition from the project report because the sponsor regards it as impractical. It would undermine the control in the reported case: A portfolio council's prior approval included a budget condition that a program now wants to ignore. The governance charter and delegated authority limits must be respected. The governing evidence supports this choice: Remove the budget condition from the project report because the sponsor regards it as impractical.
Incorrect Answers
The option describes a different design statement: gather decision-relevant evidence before acting: Examine the original approval minutes, budget caps and the proposed deviation's aggregate impact. The shortcut that conflicts with the case is remove the budget condition from the project report because the sponsor regards it as impractical. For the stated question the stronger answer is: Remove the budget condition from the project report because the sponsor regards it as impractical.
The option describes a different design statement: seek and implement the properly scoped portfolio response through authorized governance: Seek an explicit conditional-approval amendment through the correct governance authority before execution. The shortcut that conflicts with the case is remove the budget condition from the project report because the sponsor regards it as impractical. For the stated question the stronger answer is: Remove the budget condition from the project report because the sponsor regards it as impractical.
This describes a way to verify a result, not a shortcut that defeats the control: confirm the response through traceable acceptance evidence: A traceable approved amendment reconciles conditions, budget figures and the revised roadmap. The question calls for rejecting remove the budget condition from the project report because the sponsor regards it as impractical. Demonstrating and recording the portfolio outcome strengthens assurance rather than defeating it.