Question 580
While resolving an implementation issue on an adaptive/agile initiative, an AI dashboard project has an approved change for a new data source but test coverage remains based on the old schema. What should the project manager do first to address the specific problem?
Explanation
Correct Answer
Update integration tests, data definitions and traceability to reflect the approved scope. The intervention directly targets the cause described in the scenario rather than creating an unrelated process change. In this case, a change must be propagated to all affected delivery and validation artifacts. The stated constraint is: An AI dashboard project has an approved change for a new data source but test coverage remains based on the old schema. The chosen action is the most direct response under these conditions.
Incorrect Answers
Reprioritize within delegated backlog authority while checking fixed contractual commitments. This response addresses another situation in the same task area: An agile product owner wants to reorder the backlog after urgent customer feedback without changing contractual fixed deliverables. There, adaptive reprioritization is not a license to alter fixed obligations silently. For the current situation—An AI dashboard project has an approved change for a new data source but test coverage remains based on the old schema—this option would leave the specific need unresolved: a change must be propagated to all affected delivery and validation artifacts.
Reject unilateral deletion and evaluate alternative savings through the compliance-aware change board. This response addresses another situation in the same task area: A business sponsor proposes cutting a regulatory report after a cost forecast rises. There, a cost problem does not make required regulatory deliverables optional. For the current situation—An AI dashboard project has an approved change for a new data source but test coverage remains based on the old schema—this option would leave the specific need unresolved: a change must be propagated to all affected delivery and validation artifacts.
Assess performance and safety implications and route the proposed substitution through formal change control. This response addresses another situation in the same task area: A project engineer receives a verbal request to replace a specified material with a cheaper substitute. There, supplier convenience should not bypass technical and governance approval. For the current situation—An AI dashboard project has an approved change for a new data source but test coverage remains based on the old schema—this option would leave the specific need unresolved: a change must be propagated to all affected delivery and validation artifacts.