Question 520
At the next sponsor and team checkpoint on a hybrid initiative, a regional portfolio funds a digital court project but nobody has authority to resolve cross-agency release decisions. Which assignment establishes appropriate accountability for the affected decision?
Explanation
Correct Answer
Have the accountable executive sponsor chair cross-agency decisions with delegated project authority. The selected owner has authority over the specific business decision instead of transferring responsibility to an unrelated function. In this case, governance is effective only when a consequential decision has an authorized owner. The stated constraint is: A regional portfolio funds a digital court project but nobody has authority to resolve cross-agency release decisions. The chosen accountability is the most direct response under these conditions.
Incorrect Answers
Have regulatory authority approve high-risk gates and product owner manage low-risk increments. This response addresses another situation in the same task area: A hybrid product team can deploy features continuously but the regulator requires formal approval of high-impact changes. There, tailored governance protects compliance while allowing proportionate delivery agility. For the current situation—A regional portfolio funds a digital court project but nobody has authority to resolve cross-agency release decisions—this option would leave the specific need unresolved: governance is effective only when a consequential decision has an authorized owner.
Ask the board sponsor to endorse benefit oversight and the service owner to own realization. This response addresses another situation in the same task area: A nonprofit digital project reports implementation outputs but the board cannot judge public-service success. There, governance should keep decision-makers accountable for delivered value. For the current situation—A regional portfolio funds a digital court project but nobody has authority to resolve cross-agency release decisions—this option would leave the specific need unresolved: governance is effective only when a consequential decision has an authorized owner.
Have the program sponsor decide the budget change under approved thresholds. This response addresses another situation in the same task area: A defense supplier's local project lead authorizes a cost increase exceeding delegated limits. There, authority limits are meaningful only when followed for material commitments. For the current situation—A regional portfolio funds a digital court project but nobody has authority to resolve cross-agency release decisions—this option would leave the specific need unresolved: governance is effective only when a consequential decision has an authorized owner.