Question 440
While resolving an implementation issue on an adaptive/agile initiative, an adaptive team sets all story deadlines from a single optimistic velocity sprint. What should the project manager do first to address the specific problem?
Explanation
Correct Answer
Forecast delivery using observed throughput ranges and explicit uncertainty. The intervention directly targets the cause described in the scenario rather than creating an unrelated process change. In this case, empirical adaptive forecasting avoids pretending a single velocity is a certainty. The stated constraint is: An adaptive team sets all story deadlines from a single optimistic velocity sprint. The chosen action is the most direct response under these conditions.
Incorrect Answers
Validate supplier acceleration assumptions before shortening the integrated schedule. This response addresses another situation in the same task area: A construction program's supplier promises delivery six weeks earlier without changing its capacity plan. There, unsubstantiated optimism should not become a committed baseline. For the current situation—An adaptive team sets all story deadlines from a single optimistic velocity sprint—this option would leave the specific need unresolved: empirical adaptive forecasting avoids pretending a single velocity is a certainty.
Resequence work based on dependency logic instead of task duration alone. This response addresses another situation in the same task area: A manufacturing project has two tasks with the same duration but one is blocked by commissioning dependencies. There, schedule feasibility depends on precedence, not task duration alone. For the current situation—An adaptive team sets all story deadlines from a single optimistic velocity sprint—this option would leave the specific need unresolved: empirical adaptive forecasting avoids pretending a single velocity is a certainty.
Analyze critical-path impact and target recovery where it changes completion date. This response addresses another situation in the same task area: A bridge project has a critical activity delayed and a manager suggests expediting a noncritical activity instead. There, shortening work with available float may not recover the contractual finish date. For the current situation—An adaptive team sets all story deadlines from a single optimistic velocity sprint—this option would leave the specific need unresolved: empirical adaptive forecasting avoids pretending a single velocity is a certainty.