Question 320
During a project governance review on an adaptive/agile initiative, a sponsor wants to continue a costly analytics project after evidence shows target users no longer need its main report. Which assignment establishes appropriate accountability for the affected decision?
Explanation
Correct Answer
Have the investment sponsor decide continuation against updated benefit evidence. The selected owner has authority over the specific business decision instead of transferring responsibility to an unrelated function. In this case, sunk spending is not a valid reason to ignore diminished future value. The stated constraint is: A sponsor wants to continue a costly analytics project after evidence shows target users no longer need its main report. The chosen accountability is the most direct response under these conditions.
Incorrect Answers
Have faculty academic owner accept pilot value and sponsor approve scaling. This response addresses another situation in the same task area: A university digital course project can launch to one faculty now or wait until every department is ready. There, incremental value delivery reduces uncertainty without requiring every unit to launch together. For the current situation—A sponsor wants to continue a costly analytics project after evidence shows target users no longer need its main report—this option would leave the specific need unresolved: sunk spending is not a valid reason to ignore diminished future value.
Have sponsor and product owner approve the minimal integrated value slice. This response addresses another situation in the same task area: A project has limited funding and a high-value feature depends on three low-value preparatory enhancements. There, prioritization should consider dependencies while still delivering value early. For the current situation—A sponsor wants to continue a costly analytics project after evidence shows target users no longer need its main report—this option would leave the specific need unresolved: sunk spending is not a valid reason to ignore diminished future value.
Have the public-service owner define citizen value and sponsor approve redesign priorities. This response addresses another situation in the same task area: A government automation project counts forms digitized but has not reduced permit processing time. There, digitization volume is not equivalent to realized service value. For the current situation—A sponsor wants to continue a costly analytics project after evidence shows target users no longer need its main report—this option would leave the specific need unresolved: sunk spending is not a valid reason to ignore diminished future value.