Question 280
During a delivery checkpoint on an adaptive/agile initiative, a data warehouse team delivers all stated reports but users discover no source-to-metric definitions were agreed. Which assignment establishes appropriate accountability for the affected decision?
Explanation
Correct Answer
Ask business data owners to approve semantic definitions and reporting acceptance. The selected owner has authority over the specific business decision instead of transferring responsibility to an unrelated function. In this case, deliverables only meet scope when users accept what the output actually means. The stated constraint is: A data warehouse team delivers all stated reports but users discover no source-to-metric definitions were agreed. The chosen accountability is the most direct response under these conditions.
Incorrect Answers
Have product owner accept scope priority and team estimate implementation-ready stories. This response addresses another situation in the same task area: An agile claims system team confuses a high-level epic with a ready-to-implement customer story. There, adaptive scope is progressively elaborated while near-term work still needs clarity. For the current situation—A data warehouse team delivers all stated reports but users discover no source-to-metric definitions were agreed—this option would leave the specific need unresolved: deliverables only meet scope when users accept what the output actually means.
Make the designated change authority decide before contractor commitment. This response addresses another situation in the same task area: A construction project's design consultant says a landscaping enhancement was verbally authorized at a site walk. There, verbal requests should not bypass contractual change and scope controls. For the current situation—A data warehouse team delivers all stated reports but users discover no source-to-metric definitions were agreed—this option would leave the specific need unresolved: deliverables only meet scope when users accept what the output actually means.
Have the product owner order the backlog and sponsor approve fixed-date tradeoffs. This response addresses another situation in the same task area: A product team attempts to include every stakeholder suggestion in a single fixed-date release. There, scope discipline protects promised value under finite time and capacity. For the current situation—A data warehouse team delivers all stated reports but users discover no source-to-metric definitions were agreed—this option would leave the specific need unresolved: deliverables only meet scope when users accept what the output actually means.