Question 560
At a multi-team data readiness review, an AI project leader faces this situation: Modelers cannot get access to a critical dataset because two departments disagree about who can authorize use. The decision should distinguish missing evidence from confirmed data suitability. What result should the project owner require before accepting the change?
Explanation
Correct Answer
In a multi-team data readiness review, the decisive check is: An authorized owner resolves access rights and the project records the approved decision. That shows the planned action has worked: Escalate the ownership dispute with source impact, candidate authority and deadline. The governing reason is: Leadership communication should identify actionable data access obstacles and required decision owners. A separate successful activity would not establish this specific requirement.
Incorrect Answers
An access matrix must distinguish source custody, data ownership and permission to reuse information. This alternative mechanism does not match the current fault.
Raw record count alone does not establish that target classes have enough useful learning examples. Fixing that different mechanism would not address the current root cause: leadership communication should identify actionable data access obstacles and required decision owners.
Model datasets should retain source and transformation identifiers for reproducibility and audit. Its verification is distinct from the reported condition: Modelers cannot get access to a critical dataset because two departments disagree about who can authorize use. The decision should distinguish missing evidence from confirmed data suitability.