Question 420
At an enterprise maintaining a deployed AI service, an AI project leader faces this situation: A deployment team knows how to restore an earlier model but has not defined when rollback must be invoked. Governance and technical measures need accountable ongoing operation. Which principle best explains the underlying issue?
Explanation
Correct Answer
In an enterprise maintaining a deployed AI service, the underlying issue is: A release plan needs objective rollback triggers and an accountable decision process. It explains the scenario: A deployment team knows how to restore an earlier model but has not defined when rollback must be invoked. The appropriate project response is: Define thresholds for severe errors, safety signals and user impact with a tested rollback runbook. This can be checked by: An incident simulation crosses a threshold and the designated owner initiates reversal promptly.
Incorrect Answers
Recovery capability needs tested backup, provisioning and environment restoration procedures. The appropriate correction for the reported case is: Define thresholds for severe errors, safety signals and user impact with a tested rollback runbook.
Input and performance drift can degrade model reliability after the initial acceptance evaluation. Fixing that different mechanism would not address the current root cause: a release plan needs objective rollback triggers and an accountable decision process.
A blue-green strategy keeps two release environments to support cutover and possible reversal. Its verification is distinct from the reported condition: A deployment team knows how to restore an earlier model but has not defined when rollback must be invoked. Governance and technical measures need accountable ongoing operation.