Question 120
At a cross-functional AI project planning workshop, an AI project leader faces this situation: An executive confuses gross annual AI benefits with ROI after subtracting implementation costs. A viable recommendation should be measurable and clearly owned. What risk should be considered before approving the planned change?
Explanation
Correct Answer
In a cross-functional AI project planning workshop, the key precaution is: Do not mix discounted multi-year benefits with one-year costs without a consistent basis. The planned action is: Calculate ROI using agreed net benefit and cost definitions and disclose the time horizon. This caution matters because: Return on investment compares net economic gains with the investment base under stated assumptions. The team should still verify: Finance can reproduce the reported ratio from benefits, costs and the approved formula.
Incorrect Answers
User adoption depends on actual workflow utility and feedback, not installation counts alone. The appropriate correction for the reported case is: Calculate ROI using agreed net benefit and cost definitions and disclose the time horizon.
Scope must connect deliverables to objective success conditions and intended users. Fixing that different mechanism would not address the current root cause: return on investment compares net economic gains with the investment base under stated assumptions.
AI feasibility includes confirming the necessary capability under realistic workload and integration conditions. Its verification is distinct from the reported condition: An executive confuses gross annual AI benefits with ROI after subtracting implementation costs. A viable recommendation should be measurable and clearly owned.