Question 30
An independent engineer reviews this hardware-support incident: A two-PSU shelf is plugged into the same single power distribution unit despite two independent power circuits being available. Which proposed shortcut should be rejected as unsafe or technically unsound?
Explanation
Correct Answer
The shortcut creates avoidable technical, data or safety risk: Power both supplies from a single overloaded strip to simplify cabling. The proper supported response is: Review power-domain design and connect redundant supplies to appropriate independent sources per site procedure. Verify with: Trace each feed to its PDU/circuit and confirm resilience during a planned safe validation.
Incorrect Answers
The proposed activity, Choose the supported action for shelf dual input wiring: Review power-domain design and connect redundant supplies to appropriate independent sources per site procedure., is not the unsafe shortcut to reject in this shelf dual input wiring incident. The harmful behavior is: Power both supplies from a single overloaded strip to simplify cabling. Instead act by: Review power-domain design and connect redundant supplies to appropriate independent sources per site procedure.
The proposed activity, Collect operational verification for shelf dual input wiring: Trace each feed to its PDU/circuit and confirm resilience during a planned safe validation., is not the unsafe shortcut to reject in this shelf dual input wiring incident. The harmful behavior is: Power both supplies from a single overloaded strip to simplify cabling. Instead act by: Review power-domain design and connect redundant supplies to appropriate independent sources per site procedure.
The proposed activity, Escalate this shelf dual input wiring concern with exact platform, change and risk evidence before invasive service., is not the unsafe shortcut to reject in this shelf dual input wiring incident. The harmful behavior is: Power both supplies from a single overloaded strip to simplify cabling. Instead act by: Review power-domain design and connect redundant supplies to appropriate independent sources per site procedure.