Question 190
An infrastructure change review identifies: An installation map labels AOC and DAC assemblies interchangeably and technicians order the wrong reach for distant racks. Which response should the team prioritize?
Explanation
Correct Answer
Prioritize Inventory actual cable media, supported distance, vendor compatibility and bend requirements by link rather than changing unrelated components. In this case Active optical and direct-attach copper cables differ in reach, power and handling requirements; a meaningful operational test shows Each installed cable part number matches the approved link budget and passes physical and electrical checks.
Incorrect Answers
That change may help in a different context, but it would not establish that Each installed cable part number matches the approved link budget and passes physical and electrical checks. The relevant response is Inventory actual cable media, supported distance, vendor compatibility and bend requirements by link.
That change may help in a different context, but it would not establish that Each installed cable part number matches the approved link budget and passes physical and electrical checks. The relevant response is Inventory actual cable media, supported distance, vendor compatibility and bend requirements by link.
The related but distinct situation is “An engineer installs an optic that matches the physical cage but uses a wavelength incompatible with the remote transceiver”. The proposed repair must address the observed dependency: Matching connector geometry does not imply optical signaling compatibility between transceiver endpoints. For the stated problem, “Inventory actual cable media, supported distance, vendor compatibility and bend requirements by link” addresses the central condition.