Question 360
During an operational security assessment at a public-sector technology agency, the team documents this issue: Build outcome changes depending on the order unrelated pipelines share a machine. The affected delivery process supports citizen applications and reusable infrastructure; accountability and service availability depend on controlled delivery. Choose TWO statements that provide both the appropriate correction and a meaningful test of its success. (Select TWO.)
Explanation
Correct Answers
Correct corrective action. Use standardized, versioned build/test agent images with required runtimes and test tools, and isolate incompatible test workloads appropriately. The action targets the recorded failure (Build outcome changes depending on the order unrelated pipelines share a machine), and is intended to reduce the corresponding risk: Agent tool drift and shared mutable state create flaky tests and cannot reproduce failures reliably.
Correct verification. The same release test passes on a clean standard agent image and tool versions are recorded with the build. The measurement or controlled test provides evidence for the issue (Build outcome changes depending on the order unrelated pipelines share a machine) and complements the selected corrective action rather than simply repeating a recommendation.
Incorrect Answers
Require verified vulnerability, license and change-approval conditions before promotion rather than accepting a successful artifact build alone. The paired controls concern test agent and environment parity, not that measure.
A reproducible failure trend identifies the unstable test and corrective change while failures remain observable to reviewers. The test agent and environment parity implementation and safeguard are still missing.
Publish code coverage results from the test runner and enforce a focused policy for critical code without treating high percentages as proof of quality. The two-part test agent and environment parity control remains unsatisfied.