Question 710
The risk owner says a control improvement is complete: A board assumes an external audit replaces management's obligation to monitor risk continuously. What outcome would most clearly demonstrate its effectiveness?
Explanation
Correct Answer
Managers produce timely control health evidence between periodic audit engagements. This demonstrates the intended business or control result, rather than just task completion. The underlying response was: Assign continuous monitoring to process owners while preserving independent audit assurance. The evidence should relate to: Inspect first-line monitoring responsibilities, assurance scope and audit cadence.
Incorrect Answers
Operational owners approve and execute changes while oversight reviews compliance and exception trends. That would matter when a second-line risk office is directly approving every firewall change instead of challenging operational decisions. The relevant distinction in this case is: Managers produce timely control health evidence between periodic audit engagements.
The audit opinion comes from an independent function without responsibility for operating the control. That would matter when a security team reports that it performed its own independent audit of controls it designed and operates. It does not address this case's requirement: A board assumes an external audit replaces management's obligation to monitor risk continuously.
High-risk exception records show accountable owner approval and independent review. That would matter when a risk committee allows risk assessors to accept all high-risk exceptions without business-owner review. That separate mechanism does not verify the needed risk management outcome in this case.