Question 580
Before recommending action, an analyst encounters the following: A manufacturer treats residual risk as equal to the inherent risk score minus the number of installed security controls. Which check would best clarify the key uncertainty?
Explanation
Correct Answer
Review control effectiveness, independent evidence and calibrated risk methodology. This is the most direct prerequisite to validate before choosing a response. The intended controlled action is: Recalculate residual likelihood and impact based on actual control effects. Success should ultimately show: Residual rating reflects validated risk reduction rather than control count.
Incorrect Answers
Reassess existing mitigations, changed information flow and risk appetite. That would matter when an accepted residual privacy risk increases after an external processor expands data sharing beyond the agreed scope. The relevant distinction in this case is: Review control effectiveness, independent evidence and calibrated risk methodology.
Compare control effectiveness against confidentiality and availability loss pathways separately. That would matter when a backup encryption control lowers unauthorized disclosure risk but does not reduce ransomware-driven availability loss. It does not address this case's requirement: A manufacturer treats residual risk as equal to the inherent risk score minus the number of installed security controls.
Review pre-control loss scenario, redundancy evidence and remaining common dependencies. That would matter when a SaaS service has an estimated inherent outage loss of $2 million but a redundant provider reduces, not eliminates, the exposure. That separate mechanism does not verify the needed risk management outcome in this case.