Question 540
Before recommending action, an analyst encounters the following: A risk register contains risk descriptions but lacks named owners or treatment deadlines. Which check would best clarify the key uncertainty?
Explanation
Correct Answer
Inspect required register fields, ownership policy and open high-priority treatment items. This is the most direct prerequisite to validate before choosing a response. The intended controlled action is: Add accountable risk owners, treatment actions, dates and review status to each material entry. Success should ultimately show: A sample high-risk record can be followed to an authorized decision and overdue escalation.
Incorrect Answers
Compare incident identifiers, underlying scenarios, root causes and risk register history. That would matter when a branch's third-party outage is logged as a new risk each month even though it is the same unresolved dependency. The relevant distinction in this case is: Inspect required register fields, ownership policy and open high-priority treatment items.
Review implemented control evidence, remaining threat paths and the organization's acceptance procedure. That would matter when a project closes a risk record immediately after installing a compensating control without reassessing the remaining exposure. It does not address this case's requirement: A risk register contains risk descriptions but lacks named owners or treatment deadlines.
Review original owners, treatment records, exception expiry and audit history. That would matter when an acquired company's register is imported without preserving historical decisions or approved exceptions. That separate mechanism does not verify the needed risk management outcome in this case.