Question 120
After a proposed risk treatment, consider the original issue: A bank has a disaster recovery plan but has not identified which payment service must recover first. Which observable result is the BEST evidence that the response worked?
Explanation
Correct Answer
An exercise restores the highest-priority payment path within its approved time target. This demonstrates the intended business or control result, rather than just task completion. The underlying response was: Prioritize recovery sequencing by business impact and approved recovery objectives. The evidence should relate to: Run a business impact analysis for critical payments, dependencies and allowable downtime.
Incorrect Answers
Clinicians demonstrate safe access to essential workflows during the simulated identity outage. That would matter when a hospital's business continuity exercise succeeds on paper but ignores loss of its identity provider. The relevant distinction in this case is: An exercise restores the highest-priority payment path within its approved time target.
Exercises document customer effects and obtain accountable business-owner acceptance. That would matter when a telecom operator runs recovery exercises without involving the owners of customer-facing products. It does not address this case's requirement: A bank has a disaster recovery plan but has not identified which payment service must recover first.
A restore drill shows dispatch records within the approved maximum data-loss interval. That would matter when a shipping company maintains backups but has not defined the maximum tolerable loss of dispatch updates. That separate mechanism does not verify the needed risk management outcome in this case.