Question 310
A security manager is briefing business leadership, the team has started remediation after finding that a risk committee accepts a critical risk subject to a 60-day mitigation milestone. Which measurement would be most relevant for judging whether the exposure is reducing?
Explanation
Correct Answer
Measure accepted high risks past their mitigation deadline. The requirement is specific: A risk committee accepts a critical risk subject to a 60-day mitigation milestone.
Incorrect Answers
Risk monitoring must respond to changed operating conditions. It serves “during the year without updating its risk register”, not “critical risk subject to a 60-day mitigation milestone”.
Effective risk reports distinguish actionable risk from activity counts. The present requirement is “critical risk subject to a 60-day mitigation milestone”; “1,000 scanner alerts with no indication of materiality” is a distinct situation.
Lagging losses alone can miss rising exposure. That matters for “loss is stable but privileged-access bypasses increase quarterly” rather than the condition “critical risk subject to a 60-day mitigation milestone”.