Question 240
In the next assurance review, the team has started remediation after finding that an outdated partner interface creates high breach risk but contract termination would halt payroll. Which measurement would be most relevant for judging whether the exposure is reducing?
Explanation
Correct Answer
Measure residual exposure following the chosen phased treatment. Risk response must balance business consequences and acceptable residual exposure.
Incorrect Answers
Treatment should be proportionate and demonstrably effective. The deciding difference is “eliminates a common attack path” versus “breach risk but contract termination would halt payroll”.
Risk acceptance is an accountable monitored choice, not neglect. That is a different operating condition from “breach risk but contract termination would halt payroll”: “doing nothing about a minor, well-understood residual exposure”.
Stopping a risky activity can remove the scenario entirely. It serves “by moving its service to a maintained platform”, not “breach risk but contract termination would halt payroll”.