mcAfee Secure Website
23

Isaca CISA Bundle

Exam Code: CISA

Exam Name Certified Information Systems Auditor

Certification Provider: Isaca

Corresponding Certification: CISA

CISA Training Materials $44.99

Reliable & Actual Study Materials for CISA Exam Success

The Latest CISA Exam Questions as Experienced in the Actual Test!

  • 24
    Questions & Answers

    CISA Questions & Answers

    1097 Questions & Answers

    Includes questions types found on actual exam such as drag and drop, simulation, type in, and fill in the blank.

  • 25
    CISA Video Course

    CISA Training Course

    74 Video Lectures

    Based on Real Life Scenarios which you will encounter in exam and learn by working with real equipment.

  • exam =30
    Study Guide

    CISA Study Guide

    1141 PDF Pages

    Study Guide developed by industry experts who have written exams in the past. They are technology-specific IT certification researchers with at least a decade of experience at Fortune 500 companies.

exam =32

Certified Information Systems Auditor (CISA) Practice Tests

Guarantee

Satisfaction Guaranteed

Pass4sure has a remarkable Isaca Candidate Success record. We're confident of our products and provide no hassle product exchange. That's how confident we are!

99.3% Pass Rate
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • exam =34
    Questions & Answers

    Questions & Answers

    1097 Questions

    $124.99
    exam =35
  • exam =37
    CISA Video Course

    Training Course

    74 Video Lectures

    $39.99
  • exam =36
    Study Guide

    Study Guide

    1141 PDF Pages

    $29.99

Isaca CISA Practice Test 41

Question 400

During a payment-platform modernization at a payment clearing organization, the IS auditor learns that operators change runtime settings manually without updating the controlled configuration baseline. The affected operation supports merchant settlement and reconciliation. Finance and settlement integrity depend on this operation. Which risk should the auditor treat as the PRIMARY concern arising from these facts?

  1. Unauthorized or unrepeatable deployments can invalidate tested controls and complicate rollback.
  2. Without independent follow-up, unmet objectives and persistent control weaknesses may be accepted as project success.
  3. Missing input, processing, authorization or monitoring controls can allow inaccurate or unauthorized business transactions.
  4. Projects may proceed with unapproved scope, unmanaged risk or unverified business accountability.

Explanation

Correct Answer

A:

Correct. Unauthorized or unrepeatable deployments can invalidate tested controls and complicate rollback. The described exception is: operators change runtime settings manually without updating the controlled configuration baseline. This risk ties the observation to the business significance of merchant settlement and reconciliation, rather than treating management's claim as independent assurance.

Incorrect Answers

B:

Without independent follow-up, unmet objectives and persistent control weaknesses may be accepted as project success. That protection can exist while evidence appropriate to the audit conclusion is still missing.

C:

Missing input, processing, authorization or monitoring controls can allow inaccurate or unauthorized business transactions. It protects a different risk than the evidence appropriate to the audit conclusion requirement.

D:

Projects may proceed with unapproved scope, unmanaged risk or unverified business accountability. It does not retain the evidence appropriate to the audit conclusion control over time.

Question 401

During a payment-platform modernization at a payment clearing organization, the IS auditor learns that operators change runtime settings manually without updating the controlled configuration baseline. The affected operation supports merchant settlement and reconciliation. Finance and settlement integrity depend on this operation. What test BEST distinguishes effective control operation from an unsupported assertion?

  1. Recalculate total lifecycle costs and benefits, test major assumptions and assess measurable benefit ownership and feasibility.
  2. Compare the delivered service to signed requirements, realized benefits, incident data, control handover and corrective actions.
  3. Compare signed releases, configuration baselines, deployment manifests, authorization and rollback test evidence.
  4. Review the design control matrix and challenge representative high-risk workflows with negative and boundary test cases.

Explanation

Correct Answer

C:

Correct. Compare signed releases, configuration baselines, deployment manifests, authorization and rollback test evidence. The procedure directly tests the reported condition that operators change runtime settings manually without updating the controlled configuration baseline. A defensible IS audit conclusion requires relevant and reliable evidence from the actual control population and period.

Incorrect Answers

A:

Not the most direct fieldwork procedure for these facts. The evidence appropriate to the audit conclusion prerequisite remains unaddressed.

B:

Not the most direct fieldwork procedure for these facts. It changes a different feature than evidence appropriate to the audit conclusion.

D:

Not the most direct fieldwork procedure for these facts. The configuration must instead establish evidence appropriate to the audit conclusion.

Question 402

During a payment-platform modernization at a payment clearing organization, the IS auditor learns that operators change runtime settings manually without updating the controlled configuration baseline. The affected operation supports merchant settlement and reconciliation. Finance and settlement integrity depend on this operation. What result would best demonstrate sustained operation of the corrected control?

  1. Accepted design evidence and tested control cases demonstrate authorized, complete and accurate business processing.
  2. A postimplementation report reconciles expected versus actual outcomes and tracks residual issues to accountable closure.
  3. Authorized stage-gate minutes, traceable change approvals and resolved high-risk blockers support controlled project progression.
  4. Immutable release identifiers and sampled deployments reconcile to approved builds, settings and recovery plans.

Explanation

Correct Answer

D:

Correct. Immutable release identifiers and sampled deployments reconcile to approved builds, settings and recovery plans. This is stronger than a manager's verbal assurance because it can be checked against the observed issue that operators change runtime settings manually without updating the controlled configuration baseline. The reviewer must verify the remediation period and scope.

Incorrect Answers

A:

Not the strongest closure evidence for this case. The relevant success criterion is evidence appropriate to the audit conclusion; this measures a different function.

B:

Not the strongest closure evidence for this case. That result could pass without demonstrating evidence appropriate to the audit conclusion.

C:

Not the strongest closure evidence for this case. Acceptance here depends on observing evidence appropriate to the audit conclusion, not only that test.

Question 403

During a regulatory readiness review at a municipal government, the IS auditor learns that an emergency deployment has no rollback criteria or authorization evidence. The affected operation supports citizen service accounts and public records. Public accountability and essential service access are affected. Where should the audit team focus its principal finding?

  1. Incomplete or inaccurate migration can corrupt business records even when the new application starts correctly.
  2. Unauthorized or unrepeatable deployments can invalidate tested controls and complicate rollback.
  3. Projects may proceed with unapproved scope, unmanaged risk or unverified business accountability.
  4. Premature implementation can expose users to failures that realistic readiness and acceptance testing would have detected.

Explanation

Correct Answer

B:

Correct. Unauthorized or unrepeatable deployments can invalidate tested controls and complicate rollback. The described exception is: an emergency deployment has no rollback criteria or authorization evidence. This risk ties the observation to the business significance of citizen service accounts and public records, rather than treating management's claim as independent assurance.

Incorrect Answers

A:

Incomplete or inaccurate migration can corrupt business records even when the new application starts correctly. That result could pass without demonstrating evidence appropriate to the audit conclusion.

C:

Projects may proceed with unapproved scope, unmanaged risk or unverified business accountability. It does not establish the requested evidence appropriate to the audit conclusion outcome.

D:

Premature implementation can expose users to failures that realistic readiness and acceptance testing would have detected. The relevant success criterion is evidence appropriate to the audit conclusion; this measures a different function.

Question 404

During a regulatory readiness review at a municipal government, the IS auditor learns that an emergency deployment has no rollback criteria or authorization evidence. The affected operation supports citizen service accounts and public records. Public accountability and essential service access are affected. Which substantive or control test most directly addresses the observation?

  1. Map business and nonfunctional requirements to representative UAT, performance, security and operational readiness results.
  2. Compare signed releases, configuration baselines, deployment manifests, authorization and rollback test evidence.
  3. Reconcile source-to-target record counts and control totals; investigate rejected rows and test cutover and rollback.
  4. Recalculate total lifecycle costs and benefits, test major assumptions and assess measurable benefit ownership and feasibility.

Explanation

Correct Answer

B:

Correct. Compare signed releases, configuration baselines, deployment manifests, authorization and rollback test evidence. The procedure directly tests the reported condition that an emergency deployment has no rollback criteria or authorization evidence. A defensible IS audit conclusion requires relevant and reliable evidence from the actual control population and period.

Incorrect Answers

A:

Not the most direct fieldwork procedure for these facts. Acceptance here depends on observing evidence appropriate to the audit conclusion, not only that test.

C:

Not the most direct fieldwork procedure for these facts. The relevant success criterion is evidence appropriate to the audit conclusion; this measures a different function.

D:

Not the most direct fieldwork procedure for these facts. That result could pass without demonstrating evidence appropriate to the audit conclusion.

Question 405

During a regulatory readiness review at a municipal government, the IS auditor learns that an emergency deployment has no rollback criteria or authorization evidence. The affected operation supports citizen service accounts and public records. Public accountability and essential service access are affected. What outcome would provide the STRONGEST evidence that the identified gap is resolved?

  1. Authorized stage-gate minutes, traceable change approvals and resolved high-risk blockers support controlled project progression.
  2. Signed reconciliations, resolved exceptions and end-to-end business checks show migrated data are complete and accurate.
  3. Signed acceptance criteria and independent failed-case retests demonstrate the production release can meet material business and control needs.
  4. Immutable release identifiers and sampled deployments reconcile to approved builds, settings and recovery plans.

Explanation

Correct Answer

D:

Correct. Immutable release identifiers and sampled deployments reconcile to approved builds, settings and recovery plans. This is stronger than a manager's verbal assurance because it can be checked against the observed issue that an emergency deployment has no rollback criteria or authorization evidence. The reviewer must verify the remediation period and scope.

Incorrect Answers

A:

Not the strongest closure evidence for this case. It does not establish the requested evidence appropriate to the audit conclusion outcome.

B:

Not the strongest closure evidence for this case. The relevant success criterion is evidence appropriate to the audit conclusion; this measures a different function.

C:

Not the strongest closure evidence for this case. That result could pass without demonstrating evidence appropriate to the audit conclusion.

Question 406

During a post-incident audit at a retail marketplace, the IS auditor learns that release scripts reuse secrets from a development environment. The affected operation supports customer checkout and order fulfillment. Customer transactions and market trust depend on effective control. What control exposure MOST directly explains why this observation is significant?

  1. Development practices may omit critical reviews and traceability when controls are not embedded into the chosen lifecycle.
  2. Projects may proceed with unapproved scope, unmanaged risk or unverified business accountability.
  3. Without independent follow-up, unmet objectives and persistent control weaknesses may be accepted as project success.
  4. Unauthorized or unrepeatable deployments can invalidate tested controls and complicate rollback.

Explanation

Correct Answer

D:

Correct. Unauthorized or unrepeatable deployments can invalidate tested controls and complicate rollback. The described exception is: release scripts reuse secrets from a development environment. This risk ties the observation to the business significance of customer checkout and order fulfillment, rather than treating management's claim as independent assurance.

Incorrect Answers

A:

Development practices may omit critical reviews and traceability when controls are not embedded into the chosen lifecycle. It changes a different feature than evidence appropriate to the audit conclusion.

B:

Projects may proceed with unapproved scope, unmanaged risk or unverified business accountability. That change would not implement evidence appropriate to the audit conclusion.

C:

Without independent follow-up, unmet objectives and persistent control weaknesses may be accepted as project success. The configuration must instead establish evidence appropriate to the audit conclusion.

Question 407

During a post-incident audit at a retail marketplace, the IS auditor learns that release scripts reuse secrets from a development environment. The affected operation supports customer checkout and order fulfillment. Customer transactions and market trust depend on effective control. Which evidence-gathering approach is MOST aligned with the recorded exposure?

  1. Recalculate total lifecycle costs and benefits, test major assumptions and assess measurable benefit ownership and feasibility.
  2. Compare the delivered service to signed requirements, realized benefits, incident data, control handover and corrective actions.
  3. Walk through the development workflow and trace requirements, code reviews, testing and approval through representative releases.
  4. Compare signed releases, configuration baselines, deployment manifests, authorization and rollback test evidence.

Explanation

Correct Answer

D:

Correct. Compare signed releases, configuration baselines, deployment manifests, authorization and rollback test evidence. The procedure directly tests the reported condition that release scripts reuse secrets from a development environment. A defensible IS audit conclusion requires relevant and reliable evidence from the actual control population and period.

Incorrect Answers

A:

Not the most direct fieldwork procedure for these facts. That result could pass without demonstrating evidence appropriate to the audit conclusion.

B:

Not the most direct fieldwork procedure for these facts. Acceptance here depends on observing evidence appropriate to the audit conclusion, not only that test.

C:

Not the most direct fieldwork procedure for these facts. It does not establish the requested evidence appropriate to the audit conclusion outcome.

Question 408

During a post-incident audit at a retail marketplace, the IS auditor learns that release scripts reuse secrets from a development environment. The affected operation supports customer checkout and order fulfillment. Customer transactions and market trust depend on effective control. Which evidence would BEST support a conclusion that the exposure has been addressed?

  1. A sampled release has linked requirements, secure review evidence, passed tests and authorized promotion consistent with the method.
  2. Authorized stage-gate minutes, traceable change approvals and resolved high-risk blockers support controlled project progression.
  3. Immutable release identifiers and sampled deployments reconcile to approved builds, settings and recovery plans.
  4. A postimplementation report reconciles expected versus actual outcomes and tracks residual issues to accountable closure.

Explanation

Correct Answer

C:

Correct. Immutable release identifiers and sampled deployments reconcile to approved builds, settings and recovery plans. This is stronger than a manager's verbal assurance because it can be checked against the observed issue that release scripts reuse secrets from a development environment. The reviewer must verify the remediation period and scope.

Incorrect Answers

A:

Not the strongest closure evidence for this case. Acceptance here depends on observing evidence appropriate to the audit conclusion, not only that test.

B:

Not the strongest closure evidence for this case. It does not establish the requested evidence appropriate to the audit conclusion outcome.

D:

Not the strongest closure evidence for this case. That result could pass without demonstrating evidence appropriate to the audit conclusion.

Question 409

During a routine controls assessment at a regional hospital, the IS auditor learns that a migrated customer ledger total differs from the legacy system's validated closing balance. The affected operation supports patient-care scheduling and claims processing. Healthcare service continuity and protected records are at stake. Which consequence would MOST directly follow if this weakness remains unresolved?

  1. Unverified cost, feasibility or benefit assumptions can justify a project that fails to deliver enterprise value.
  2. Without independent follow-up, unmet objectives and persistent control weaknesses may be accepted as project success.
  3. Incomplete or inaccurate migration can corrupt business records even when the new application starts correctly.
  4. Premature implementation can expose users to failures that realistic readiness and acceptance testing would have detected.

Explanation

Correct Answer

C:

Correct. Incomplete or inaccurate migration can corrupt business records even when the new application starts correctly. The described exception is: a migrated customer ledger total differs from the legacy system's validated closing balance. This risk ties the observation to the business significance of patient-care scheduling and claims processing, rather than treating management's claim as independent assurance.

Incorrect Answers

A:

Unverified cost, feasibility or benefit assumptions can justify a project that fails to deliver enterprise value. The evidence appropriate to the audit conclusion prerequisite remains unaddressed.

B:

Without independent follow-up, unmet objectives and persistent control weaknesses may be accepted as project success. It changes a different feature than evidence appropriate to the audit conclusion.

D:

Premature implementation can expose users to failures that realistic readiness and acceptance testing would have detected. The configuration must instead establish evidence appropriate to the audit conclusion.

Question 410

During a routine controls assessment at a regional hospital, the IS auditor learns that a migrated customer ledger total differs from the legacy system's validated closing balance. The affected operation supports patient-care scheduling and claims processing. Healthcare service continuity and protected records are at stake. Which audit procedure would provide the MOST DIRECT evidence about this control?

  1. Walk through the development workflow and trace requirements, code reviews, testing and approval through representative releases.
  2. Compare the delivered service to signed requirements, realized benefits, incident data, control handover and corrective actions.
  3. Map business and nonfunctional requirements to representative UAT, performance, security and operational readiness results.
  4. Reconcile source-to-target record counts and control totals; investigate rejected rows and test cutover and rollback.

Explanation

Correct Answer

D:

Correct. Reconcile source-to-target record counts and control totals; investigate rejected rows and test cutover and rollback. The procedure directly tests the reported condition that a migrated customer ledger total differs from the legacy system's validated closing balance. A defensible IS audit conclusion requires relevant and reliable evidence from the actual control population and period.

Incorrect Answers

A:

Not the most direct fieldwork procedure for these facts. The relevant success criterion is evidence appropriate to the audit conclusion; this measures a different function.

B:

Not the most direct fieldwork procedure for these facts. That result could pass without demonstrating evidence appropriate to the audit conclusion.

C:

Not the most direct fieldwork procedure for these facts. Acceptance here depends on observing evidence appropriate to the audit conclusion, not only that test.