Question 850
What is the clearest security consequence when a factory security test is performed on a different firmware build from the units delivered?
Explanation
Correct Answer
The unmitigated condition can produce this failure; test remediation by confirming that the delivered build number matches the evidence package.
Incorrect Answers
That concern does not address the immediate risk: different revisions can invalidate supplier test conclusions.
This failure can arise in Test defect disposition, for example where a CFAT finds that one vendor account bypasses MFA but the project labels the test passed. Here the direct exposure is that different revisions can invalidate supplier test conclusions.
It would matter for Configuration as-built; the reported weakness instead threatens that different revisions can invalidate supplier test conclusions.