Question 820
A process installation has a concern where a vendor calls a controller secure because one penetration test passed but has no vulnerability handling process. Which failure is most likely to matter?
Explanation
Correct Answer
This consequence is specific to the industrial control path described. The corrective approach is to evaluate the supplier's secure product development and maintenance processes.
Incorrect Answers
This describes the separate issue of Security level verification. For the current system, part 4-1 concerns secure development lifecycle processes.
It would matter for Compensating measures; the reported weakness instead threatens that a single test cannot replace ongoing secure product engineering.
That concern does not address the immediate risk: a single test cannot replace ongoing secure product engineering.