Question 60
Which recorded result would establish the control is working when a factory collects alerts but has no mechanism for responders to access them during a shift?
Explanation
Correct Answer
The acceptance result directly demonstrates the requirement has been met. The enabling measure is to provide usable alerts, monitored logs, and accountable response procedures; foundational requirement TRE addresses usable security event visibility and response.
Incorrect Answers
The proposed result does not show that a high-priority test event reaches the on-duty operator in time.
The stated evidence would be appropriate for Use control. This design instead needs to show that a high-priority test event reaches the on-duty operator in time.
This check belongs to Zone-specific targets. For the current issue, acceptance should establish that a high-priority test event reaches the on-duty operator in time.