Question 560
A commissioning team sees that an approved CRS is modified by a vendor after the design freeze with no impact assessment. Which TWO choices specify a control and an observable result?
Explanation
Correct Answers
The evidence links the outcome to the security mechanism: requirements are controlled engineering baselines throughout implementation. The corresponding design step is to version the specification and perform risk and test impact review for changed requirements.
Requirements are controlled engineering baselines throughout implementation. Confirm completion when the change log identifies affected drawings, rules, and tests.
Incorrect Answers
The proposed result does not show that the change log identifies affected drawings, rules, and tests.
This measure is useful for Validation responsibility, where a CRS lists a security control but leaves test owner and environment undefined. In the present case, uncontrolled requirement edits can invalidate prior design acceptance; the targeted response is different.