Question 600
During an assessment planning meeting, the team encounters this situation: A dairy plant tour reveals an unmanaged switch between an HMI and the production network. Which action is the most directly appropriate next step?
Explanation
Correct Answer
Record physical topology and validate the discovered pathway with site personnel. Observed assets and links require reconciliation rather than selective omission. The team can check its effectiveness by doing the following: Produce an annotated drawing and photographs authorized under site policy, with asset IDs.
Incorrect Answers
Validate automated findings against product, version, configuration and reachable path before ranking. The plant scenario instead hinges on: Record physical topology and validate the discovered pathway with site personnel.
Reassess the changed boundary and update risk evidence rather than only closing the ticket. The plant scenario instead hinges on: Record physical topology and validate the discovered pathway with site personnel.
Pilot active methods against a representative test asset, then obtain explicit production approval. The plant scenario instead hinges on: Record physical topology and validate the discovered pathway with site personnel.