Question 340
During assurance review of this condition, which statement creates an unjustified risk claim? A planned desalination train will connect packaged skids to a plantwide supervisory system.
Explanation
Correct Answer
Postpone all cyber risk work until after the line is energized. Early design review can correct boundary errors before equipment and contracts become difficult to change. The defensible alternative is: Review proposed trust boundaries and data paths before design freeze and procurement approval. A validation check is: Produce a reviewed connectivity diagram and security requirements trace for vendor interfaces.
Incorrect Answers
Confirm an authorized action: Review proposed trust boundaries and data paths before design freeze and procurement approval. This is not the unsupported shortcut; that shortcut is: Postpone all cyber risk work until after the line is energized.
This calls for verifiable assessment evidence, which is appropriate for the stated case: Produce a reviewed connectivity diagram and security requirements trace for vendor interfaces. It does not make the unsupported claim: Postpone all cyber risk work until after the line is energized.
Document the assessment rationale: Early design review can correct boundary errors before equipment and contracts become difficult to change. The question instead identifies this specific unsupported inference: Postpone all cyber risk work until after the line is energized.