Question 110
An assessor is asked to advise on this site condition: A gas compressor site still circulates schematics from before a network separation project. What should the team prioritize?
Explanation
Correct Answer
Use revision-controlled network drawings tied to a dated configuration baseline. Versioned evidence keeps the assessment traceable as the real installation evolves. The team can check its effectiveness by doing the following: Obtain operations signoff on the current topology revision and list unresolved mismatches.
Incorrect Answers
Reconcile site walkdown findings against the current asset inventory and as-built network diagram. The plant scenario instead hinges on: Use revision-controlled network drawings tied to a dated configuration baseline.
Review proposed trust boundaries and data paths before design freeze and procurement approval. The plant scenario instead hinges on: Use revision-controlled network drawings tied to a dated configuration baseline.
Identify third-party identities, remote entry points, privileges, time windows, and revocation responsibilities. The plant scenario instead hinges on: Use revision-controlled network drawings tied to a dated configuration baseline.