Question 290
A campus network design engagement reports: The procurement board sees a change from two to four access switches but no signed scope decision. Which action should the HPE campus access architect prioritize?
Explanation
Correct Answer
The important design distinction is that quantity changes require traceable business approval and technical justification.. Therefore provide a costed change request linked to new port demand and revised drawings.. Verify it through The change log explains each added device and its budget effect.
Incorrect Answers
Although appropriate for a different engagement—A retailer's executives ask whether the proposal is still valid after a planned office closure changes the site count.—this action does not meet the specific requirement. Acceptance here depends on The change log explains each added device and its budget effect..
This alternative addresses the separate case “A technical committee notices the new routed topology has no documented return path for guest internet traffic”. Independent review can expose routing assumptions missed by the original designer. The deciding requirement here is “Provide a costed change request linked to new port demand and revised drawings”.
Resolve audit responsibility, retention, and access controls with compliance reviewers. is a sensible intervention when A regulator requires an audit trail for privileged network changes, but the preliminary operations model has no logging owner.; it leaves this customer's principal constraint unresolved. The decisive evidence here would be The change log explains each added device and its budget effect..