Question 220
A campus network design engagement reports: A basement IDF has a cooling limit below the proposed switch stack's combined heat output. Which action should the HPE campus access architect prioritize?
Explanation
Correct Answer
Include equipment thermal output and closet cooling capacity in topology and BOM validation. addresses the stated customer requirement because electronics may fail or require derating if installed heat load exceeds room capacity.. Acceptance should confirm: The engineering schedule demonstrates sufficient cooling for expected operation.
Incorrect Answers
Although appropriate for a different engagement—A guest WLAN is mapped directly into the research server VLAN to avoid adding firewall rules.—this action does not meet the specific requirement. Acceptance here depends on The engineering schedule demonstrates sufficient cooling for expected operation..
The stated alternative concerns Two distribution switches are expected to protect a core failure but are physically powered from one nonredundant feed.. Applying it first here would bypass the need established by this customer's facts: electronics may fail or require derating if installed heat load exceeds room capacity..
Trace every path's link speeds and bottlenecks before asserting active-active capacity. is a sensible intervention when An aggregation pair has symmetric uplinks on paper but one path traverses a slow intermediate switch.; it leaves this customer's principal constraint unresolved. The decisive evidence here would be The engineering schedule demonstrates sufficient cooling for expected operation..