Question 410
At Evergreen Grid, the facility wants an IEC 62443 assessment but only submits a generic web vulnerability report. The relevant endpoint is transformer control bay X-13; the risk register needs evidence that would be meaningful to a second reviewer. The implementation team tried “Ignore vendor remote access because it is outside the controller subnet.” and the change did not satisfy the OT acceptance criteria. Which corrective step is most appropriately scoped?
Explanation
Correct Answer
A generic IT scan lacks OT zone design and process-specific control context needed for industrial security review. The operational owner should approve the controlled window.
Incorrect Answers
The relevant design is: Scope assessed zones, conduits, asset roles and control evidence against the applicable IEC 62443 requirements.
A generic IT scan lacks OT zone design and process-specific control context needed for industrial security review. Specific validation is still needed: Trace a selected zone/conduit to the applicable control objective, configuration evidence and accountable assessor.
A plant-wide suspension would break least-privilege controls and exceed the local problem scope. A generic IT scan lacks OT zone design and process-specific control context needed for industrial security review. Containment and recovery should be limited to the affected path.